(1) Where the buyer receives notification of a material or indefinite delay or an allocation justified under the preceding section he may by written notification to the seller as to any delivery concerned, and where the prospective deficiency substantially impairs the value of the whole contract under the provisions of this Article relating to breach of installment contracts (Section 2-612), then also as to the whole,
(2) If after receipt of such notification from the seller the buyer fails so to modify the contract within a reasonable time not exceeding thirty days the contract lapses with respect to any deliveries affected.
(3) The provisions of this section may not be negated by agreement except in so far as the seller has assumed a greater obligation under the preceding section.s
© Copyright 2005 by The American Law Institute and the National Conference of Commissioners on Uniform State Laws; reproduced, published and distributed with the permission of the Permanent Editorial Board for the Uniform Commercial Code for the limited purposes of study, teaching, and academic research.