10 U.S. Code § 2304a - Task and delivery order contracts: general authority

(a) Authority To Award.— Subject to the requirements of this section, section 2304c of this title, and other applicable law, the head of an agency may enter into a task or delivery order contract (as defined in section 2304d of this title) for procurement of services or property.
(b) Solicitation.— The solicitation for a task or delivery order contract shall include the following:
(1) The period of the contract, including the number of options to extend the contract and the period for which the contract may be extended under each option, if any.
(2) The maximum quantity or dollar value of the services or property to be procured under the contract.
(3) A statement of work, specifications, or other description that reasonably describes the general scope, nature, complexity, and purposes of the services or property to be procured under the contract.
(c) Applicability of Restriction on Use of Noncompetitive Procedures.— The head of an agency may use procedures other than competitive procedures to enter into a task or delivery order contract under this section only if an exception in subsection (c) ofsection 2304 of this title applies to the contract and the use of such procedures is approved in accordance with subsection (f) of such section.
(d) Single and Multiple Contract Awards.—
(1) The head of an agency may exercise the authority provided in this section—
(A) to award a single task or delivery order contract; or
(B) if the solicitation states that the head of the agency has the option to do so, to award separate task or delivery order contracts for the same or similar services or property to two or more sources.
(2) No determination under section 2304 (b) of this title is required for award of multiple task or delivery order contracts under paragraph (1)(B).
(3) No task or delivery order contract in an amount estimated to exceed $100,000,000 (including all options) may be awarded to a single source unless the head of the agency determines in writing that—
(A) the task or delivery orders expected under the contract are so integrally related that only a single source can reasonably perform the work;
(B) the contract provides only for firm, fixed price task orders or delivery orders for—
(i) products for which unit prices are established in the contract; or
(ii) services for which prices are established in the contract for the specific tasks to be performed;
(C) only one source is qualified and capable of performing the work at a reasonable price to the government; or
(D) because of exceptional circumstances, it is necessary in the public interest to award the contract to a single source.
(4) The regulations implementing this subsection shall—
(A) establish a preference for awarding, to the maximum extent practicable, multiple task or delivery order contracts for the same or similar services or property under the authority of paragraph (1)(B); and
(B) establish criteria for determining when award of multiple task or delivery order contracts would not be in the best interest of the Federal Government.
(e) Contract Modifications.— A task or delivery order may not increase the scope, period, or maximum value of the task or delivery order contract under which the order is issued. The scope, period, or maximum value of the contract may be increased only by modification of the contract.
(f) Contract Period.— The head of an agency entering into a task or delivery order contract under this section may provide for the contract to cover any period up to five years and may extend the contract period for one or more successive periods pursuant to an option provided in the contract or a modification of the contract. The total contract period as extended may not exceed 10 years unless such head of an agency determines in writing that exceptional circumstances necessitate a longer contract period.
(g) Inapplicability to Contracts for Advisory and Assistance Services.— Except as otherwise specifically provided in section 2304b of this title, this section does not apply to a task or delivery order contract for the procurement of advisory and assistance services (as defined in section 1105 (g) of title 31).
(h) Relationship to Other Contracting Authority.— Nothing in this section may be construed to limit or expand any authority of the head of an agency or the Administrator of General Services to enter into schedule, multiple award, or task or delivery order contracts under any other provision of law.

Source

(Added Pub. L. 103–355, title I, § 1004(a)(1),Oct. 13, 1994, 108 Stat. 3249; amended Pub. L. 108–136, div. A, title VIII, § 843(b),Nov. 24, 2003, 117 Stat. 1553; Pub. L. 108–375, div. A, title VIII, § 813(a),Oct. 28, 2004, 118 Stat. 2014; Pub. L. 110–181, div. A, title VIII, § 843(a)(1),Jan. 28, 2008, 122 Stat. 236; Pub. L. 111–84, div. A, title VIII, § 814(a),Oct. 28, 2009, 123 Stat. 2407; Pub. L. 112–81, div. A, title VIII, § 809(b),Dec. 31, 2011, 125 Stat. 1490.)
Codification

Another section 2304a was renumbered section 2304e of this title.
Amendments

2011—Subsec. (d)(3). Pub. L. 112–81struck out subpar. (A) designation before “No task”, redesignated cls. (i) to (iv) of former subpar. (A) as subpars. (A) to (D), respectively, of par. (3), redesignated subcls. (I) and (II) of former cl. (ii) as cls. (i) and (ii), respectively, of subpar. (B), and struck out former subpar. (B) which read as follows: “The head of the agency shall notify the congressional defense committees within 30 days after any determination under clause (i), (ii), (iii), or (iv) of subparagraph (A).”
2009—Subsec. (d)(3)(B). Pub. L. 111–84amended subpar. (B) generally. Prior to amendment, subpar. (B) read as follows: “The head of the agency shall notify Congress within 30 days after any determination under subparagraph (A)(iv).”
2008—Subsec. (d)(3), (4). Pub. L. 110–181added par. (3) and redesignated former par. (3) as (4).
2004—Subsec. (f). Pub. L. 108–375substituted “any period up to five years and may extend the contract period for one or more successive periods pursuant to an option provided in the contract or a modification of the contract. The total contract period as extended may not exceed 10 years unless such head of an agency determines in writing that exceptional circumstances necessitate a longer contract period” for “a total period of not more than five years”.
2003—Subsecs. (f) to (h). Pub. L. 108–136added subsec. (f) and redesignated former subsecs. (f) and (g) as (g) and (h), respectively.
Effective Date of 2008 Amendment

Pub. L. 110–181, div. A, title VIII, § 843(a)(3)(A),Jan. 28, 2008, 122 Stat. 237, provided that: “The amendments made by paragraph (1) [amending this section] shall take effect on the date that is 120 days after the date of the enactment of this Act [Jan. 28, 2008], and shall apply with respect to any contract awarded on or after such date.”
Effective Date

For effective date and applicability of section, see section 10001 ofPub. L. 103–355, set out as an Effective Date of 1994 Amendment note under section 2302 of this title.
Congressional Intelligence Committees

Pub. L. 111–84, div. A, title VIII, § 814(b),Oct. 28, 2009, 123 Stat. 2407, provided that: “In the case of a task or delivery order contract awarded with respect to intelligence activities of the Department of Defense, any notification provided under [former] subparagraph (B) of section 2304a (d)(3) of title 10, United States Code, as amended by subsection (a), shall also be provided at the same time as notification is provided to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] under that subparagraph—
“(1) to the Permanent Select Committee on Intelligence of the House of Representatives insofar as such task or delivery order contract relates to tactical intelligence and intelligence-related activities of the Department; and
“(2) to the Select Committee on Intelligence of the Senate and the Permanent Select Committee on Intelligence of the House of Representatives insofar as such task or delivery order contract relates to intelligence and intelligence-related activities of the Department other than those specified in paragraph (1).”
Provisions Not Affected by Pub. L. 103–355

Pub. L. 103–355, title I, § 1004(d),Oct. 13, 1994, 108 Stat. 3253, as amended by Pub. L. 108–136, div. A, title X, § 1045(f),Nov. 24, 2003, 117 Stat. 1613, provided that: “Nothing in section 2304a, 2304b, 2304c, or 2304d of title 10, United States Code, as added by subsection (a), and nothing in the amendments made by subsections (b) and (c) [amending sections 2304 and 2331 of this title], shall be construed as modifying or superseding, or as intended to impair or restrict, authorities or responsibilities under chapter 11 of title 40, United States Code.”

The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.

The most recent Classification Table update that we have noticed was Tuesday, August 13, 2013

An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.

10 USCDescription of ChangeSession YearPublic LawStatutes at Large

This is a list of parts within the Code of Federal Regulations for which this US Code section provides rulemaking authority.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


32 CFR - National Defense

32 CFR Part 272 - ADMINISTRATION AND SUPPORT OF BASIC RESEARCH BY THE DEPARTMENT OF DEFENSE

33 CFR - Navigation and Navigable Waters

33 CFR Part 210 - PROCUREMENT ACTIVITIES OF THE CORPS OF ENGINEERS

48 CFR - Federal Acquisition Regulations System

48 CFR Part 1 - FEDERAL ACQUISITION REGULATIONS SYSTEM

48 CFR Part 2 - DEFINITIONS OF WORDS AND TERMS

48 CFR Part 3 - IMPROPER BUSINESS PRACTICES AND PERSONAL CONFLICTS OF INTEREST

48 CFR Part 4 - ADMINISTRATIVE MATTERS

48 CFR Part 5 - PUBLICIZING CONTRACT ACTIONS

48 CFR Part 6 - COMPETITION REQUIREMENTS

48 CFR Part 7 - ACQUISITION PLANNING

48 CFR Part 8 - REQUIRED SOURCES OF SUPPLIES AND SERVICES

48 CFR Part 9 - CONTRACTOR QUALIFICATIONS

48 CFR Part 10 - MARKET RESEARCH

48 CFR Part 11 - DESCRIBING AGENCY NEEDS

48 CFR Part 12 - ACQUISITION OF COMMERCIAL ITEMS

48 CFR Part 13 - SIMPLIFIED ACQUISITION PROCEDURES

48 CFR Part 14 - SEALED BIDDING

48 CFR Part 15 - CONTRACTING BY NEGOTIATION

48 CFR Part 16 - TYPES OF CONTRACTS

48 CFR Part 17 - SPECIAL CONTRACTING METHODS

48 CFR Part 18 19

48 CFR Part 22 - APPLICATION OF LABOR LAWS TO GOVERNMENT ACQUISITIONS

48 CFR Part 23 - ENVIRONMENT, ENERGY AND WATER EFFICIENCY, RENEWABLE ENERGY TECHNOLOGIES, OCCUPATIONAL SAFETY, AND DRUG-FREE WORKPLACE

48 CFR Part 24 - PROTECTION OF PRIVACY AND FREEDOM OF INFORMATION

48 CFR Part 25 - FOREIGN ACQUISITION

48 CFR Part 26 - OTHER SOCIOECONOMIC PROGRAMS

48 CFR Part 27 - PATENTS, DATA, AND COPYRIGHTS

48 CFR Part 28 - BONDS AND INSURANCE

48 CFR Part 29 - TAXES

48 CFR Part 30 - COST ACCOUNTING STANDARDS ADMINISTRATION

48 CFR Part 31 - CONTRACT COST PRINCIPLES AND PROCEDURES

48 CFR Part 32 - CONTRACT FINANCING

48 CFR Part 33 - PROTESTS, DISPUTES, AND APPEALS

48 CFR Part 34 - MAJOR SYSTEM ACQUISITION

48 CFR Part 35 - RESEARCH AND DEVELOPMENT CONTRACTING

48 CFR Part 36 - CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS

48 CFR Part 37 - SERVICE CONTRACTING

48 CFR Part 38 - FEDERAL SUPPLY SCHEDULE CONTRACTING

48 CFR Part 39 - ACQUISITION OF INFORMATION TECHNOLOGY

48 CFR Part 41 - ACQUISITION OF UTILITY SERVICES

48 CFR Part 42 - CONTRACT ADMINISTRATION AND AUDIT SERVICES

48 CFR Part 43 - CONTRACT MODIFICATIONS

48 CFR Part 44 - SUBCONTRACTING POLICIES AND PROCEDURES

48 CFR Part 45 - GOVERNMENT PROPERTY

48 CFR Part 46 - QUALITY ASSURANCE

48 CFR Part 47 - TRANSPORTATION

48 CFR Part 48 - VALUE ENGINEERING

48 CFR Part 49 - TERMINATION OF CONTRACTS

48 CFR Part 50 - EXTRAORDINARY CONTRACTUAL ACTIONS AND THE SAFETY ACT

48 CFR Part 51 - USE OF GOVERNMENT SOURCES BY CONTRACTORS

48 CFR Part 52 - SOLICITATION PROVISIONS AND CONTRACT CLAUSES

48 CFR Part 53 - FORMS

48 CFR Part 5433 - PROTESTS, DISPUTES AND APPEALS

 

LII has no control over and does not endorse any external Internet site that contains links to or references LII.