10 USC § 2433a - Critical cost growth in major defense acquisition programs
(a)
Reassessment of Program.—
If the program acquisition unit cost or procurement unit cost of a major defense acquisition program or designated subprogram (as determined by the Secretary under section
2433
(d) of this title) increases by a percentage equal to or greater than the critical cost growth threshold for the program or subprogram, the Secretary of Defense, after consultation with the Joint Requirements Oversight Council regarding program requirements, shall—
(1)
determine the root cause or causes of the critical cost growth in accordance with applicable statutory requirements and Department of Defense policies, procedures, and guidance; and
(2)
in consultation with the Director of Cost Assessment and Program Evaluation, carry out an assessment of—
(B)
the projected cost of completing the program based on reasonable modification of such requirements;
(b)
Presumption of Termination.—
(1)
After conducting the reassessment required by subsection (a) with respect to a major defense acquisition program, the Secretary shall terminate the program unless the Secretary submits to Congress, before the end of the 60-day period beginning on the day the Selected Acquisition Report containing the information described in section
2433
(g) of this title is required to be submitted under section
2432
(f) of this title, a written certification in accordance with paragraph (2).
(2)
A certification described by this paragraph with respect to a major defense acquisition program is a written certification that—
(B)
there are no alternatives to the program which will provide acceptable capability to meet the joint military requirement (as defined in section
181
(g)(1) of this title) at less cost;
(C)
the new estimates of the program acquisition unit cost or procurement unit cost have been determined by the Director of Cost Assessment and Program Evaluation to be reasonable;
(3)
A written certification under paragraph (2) shall be accompanied by a report presenting the root cause analysis and assessment carried out pursuant to subsection (a) and the basis for each determination made in accordance with subparagraphs (A) through (E) of paragraph (2), together with supporting documentation.
(c)
Actions if Program Not Terminated.—
(1)
If the Secretary elects not to terminate a major defense acquisition program pursuant to subsection (b), the Secretary shall—
(A)
restructure the program in a manner that addresses the root cause or causes of the critical cost growth, as identified pursuant to subsection (a), and ensures that the program has an appropriate management structure as set forth in the certification submitted pursuant to subsection (b)(2)(E);
(B)
rescind the most recent Milestone approval for the program and withdraw any associated certification under section
2366a or
2366b of this title;
(C)
require a new Milestone approval for the program before taking any contract action to enter a new contract, exercise an option under an existing contract, or otherwise extend the scope of an existing contract under the program, except to the extent determined necessary by the Milestone Decision Authority, on a non-delegable basis, to ensure that the program can be restructured as intended by the Secretary without unnecessarily wasting resources;
(2)
For purposes of paragraph (1)(D), the report specified in this paragraph is the first Selected Acquisition Report for the program submitted pursuant to section
2432 of this title after the President submits a budget pursuant to section
1105 of title
31, in the calendar year following the year in which the program was restructured.
(3)
(A)
The requirements of subparagraphs (B), (C), and (E) of paragraph (1) shall not apply to a program or subprogram if—
(i)
the Milestone Decision Authority determines in writing, on the basis of a cost assessment and root cause analysis conducted pursuant to subsection (a), that—
(I)
but for a change in the quantity of items to be purchased under the program or subprogram, the program acquisition unit cost or procurement unit cost for the program or subprogram would not have increased by a percentage equal to or greater than the cost growth thresholds for the program or subprogram set forth in subparagraph (B); and
(ii)
the Secretary determines in writing that the cost to the Department of Defense of complying with such requirements is likely to exceed the benefits to the Department of complying with such requirements; and
(iii)
the Secretary submits to Congress, before the end of the 60-day period beginning on the day the Selected Acquisition Report containing the information described in section
2433
(g) of this title is required to be submitted under section
2432
(f) of this title—
(B)
The cost growth thresholds specified in this subparagraph are as follows:
(i)
In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
(ii)
In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
(a)
Reassessment of Program.—
If the program acquisition unit cost or procurement unit cost of a major defense acquisition program or designated subprogram (as determined by the Secretary under section
2433
(d) of this title) increases by a percentage equal to or greater than the critical cost growth threshold for the program or subprogram, the Secretary of Defense, after consultation with the Joint Requirements Oversight Council regarding program requirements, shall—
(1)
determine the root cause or causes of the critical cost growth in accordance with applicable statutory requirements and Department of Defense policies, procedures, and guidance; and
(2)
in consultation with the Director of Cost Assessment and Program Evaluation, carry out an assessment of—
(B)
the projected cost of completing the program based on reasonable modification of such requirements;
(b)
Presumption of Termination.—
(1)
After conducting the reassessment required by subsection (a) with respect to a major defense acquisition program, the Secretary shall terminate the program unless the Secretary submits to Congress, before the end of the 60-day period beginning on the day the Selected Acquisition Report containing the information described in section
2433
(g) of this title is required to be submitted under section
2432
(f) of this title, a written certification in accordance with paragraph (2).
(2)
A certification described by this paragraph with respect to a major defense acquisition program is a written certification that—
(B)
there are no alternatives to the program which will provide acceptable capability to meet the joint military requirement (as defined in section
181
(g)(1) of this title) at less cost;
(C)
the new estimates of the program acquisition unit cost or procurement unit cost have been determined by the Director of Cost Assessment and Program Evaluation to be reasonable;
(3)
A written certification under paragraph (2) shall be accompanied by a report presenting the root cause analysis and assessment carried out pursuant to subsection (a) and the basis for each determination made in accordance with subparagraphs (A) through (E) of paragraph (2), together with supporting documentation.
(c)
Actions if Program Not Terminated.—
(1)
If the Secretary elects not to terminate a major defense acquisition program pursuant to subsection (b), the Secretary shall—
(A)
restructure the program in a manner that addresses the root cause or causes of the critical cost growth, as identified pursuant to subsection (a), and ensures that the program has an appropriate management structure as set forth in the certification submitted pursuant to subsection (b)(2)(E);
(B)
rescind the most recent Milestone approval for the program and withdraw any associated certification under section
2366a or
2366b of this title;
(C)
require a new Milestone approval for the program before taking any contract action to enter a new contract, exercise an option under an existing contract, or otherwise extend the scope of an existing contract under the program, except to the extent determined necessary by the Milestone Decision Authority, on a non-delegable basis, to ensure that the program can be restructured as intended by the Secretary without unnecessarily wasting resources;
(2)
For purposes of paragraph (1)(D), the report specified in this paragraph is the first Selected Acquisition Report for the program submitted pursuant to section
2432 of this title after the President submits a budget pursuant to section
1105 of title
31, in the calendar year following the year in which the program was restructured.
(3)
(A)
The requirements of subparagraphs (B) and (C) of paragraph (1) shall not apply to a program or subprogram if—
(i)
the Milestone Decision Authority determines in writing, on the basis of a cost assessment and root cause analysis conducted pursuant to subsection (a), that—
(I)
but for a change in the quantity of items to be purchased under the program or subprogram, the program acquisition unit cost or procurement unit cost for the program or subprogram would not have increased by a percentage equal to or greater than the cost growth thresholds for the program or subprogram set forth in subparagraph (B); and
(ii)
the Secretary determines in writing that the cost to the Department of Defense of complying with such requirements is likely to exceed the benefits to the Department of complying with such requirements; and
(iii)
the Secretary submits to Congress, before the end of the 60-day period beginning on the day the Selected Acquisition Report containing the information described in section
2433
(g) of this title is required to be submitted under section
2432
(f) of this title—
(B)
The cost growth thresholds specified in this subparagraph are as follows:
(i)
In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
(ii)
In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
Source
(Added Pub. L. 111–23, title II, § 206(a)(1),May 22, 2009, 123 Stat. 1726; amended Pub. L. 111–383, div. A, title X, § 1075(b)(35),Jan. 7, 2011, 124 Stat. 4371; Pub. L. 112–81, div. A, title VIII, §§ 801(e)(4),
831,Dec. 31, 2011, 125 Stat. 1484, 1503.)
References in Text
Section 205 of the Weapon Systems Acquisition Reform Act of 2009, referred to in subsec. (c)(1)(E), is section 205 ofPub. L. 111–23, which amended section
2366b of this title and enacted provisions set out as notes under this section and section
2366b of this title.
Amendments
Subsec. (c)(1)(B), (C). Pub. L. 112–81, § 801(e)(4), struck out “, or Key Decision Point approval in the case of a space program,” after “Milestone approval”.
Subsec. (c)(3). Pub. L. 112–81, § 831, added par. (3).
Reviews of Programs Restructured After Experiencing Critical Cost Growth
Pub. L. 111–23, title II, § 205(c),May 22, 2009, 123 Stat. 1725, as amended by Pub. L. 111–383, div. A, title VIII, § 813(e), title X, § 1075(k)(2),Jan. 7, 2011, 124 Stat. 4266, 4378, provided that: “The official designated to perform oversight of performance assessment pursuant to section 103 of this Act [set out as a note under section
2430 of this title], shall assess the performance of each major defense acquisition program that has exceeded critical cost growth thresholds established pursuant to section
2433
(e) of title
10, United States Code, but has not been terminated in accordance with section 2433a of such title (as added by section 206(a) of this Act) not less often than semi-annually until one year after the date on which such program receives a new milestone approval, in accordance with section 2433a(c)(1)(C) of such title (as so added). The results of reviews performed under this subsection shall be reported to the Under Secretary of Defense for Acquisition, Technology, and Logistics and summarized in the next annual report of such designated official.”
[Pub. L. 111–383, div. A, title VIII, § 813(e),Jan. 7, 2011, 124 Stat. 4266, provided that the amendment made by section
813
(e) tosection 205(c) ofPub. L. 111–23, set out above, is effective as of May 22, 2009, and as if included in Pub. L. 111–23, as enacted.]
[For definition of “major defense acquisition program” as used in section 205(c) ofPub. L. 111–23, set out above, see section 2(2) ofPub. L. 111–23, set out as a note under section
2430 of this title.]
The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.
The most recent Classification Table update that we have noticed was Wednesday, May 29, 2013
An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.
| 10 USC | Description of Change | Session Year | Public Law | Statutes at Large |
|---|---|---|---|---|
| § 2433a | 2012 | 112-239 [Sec.] 813 | 126 Stat. 1829 |