22 U.S.C. § 2421f - Sustainability requirements for certain capital projects in connection with overseas contingency operations
(a)
Limitation
(1)
In general
Commencing 60 days after January 2, 2013—
(A)
amounts authorized to be appropriated for the Department of Defense may not be obligated or expended for a capital project described in subsection (b) unless the Secretary of Defense, in consultation with the United States commander of military operations in the country in which the project will be carried out, completes an assessment on the necessity and sustainability of the project;
(B)
amounts authorized to be appropriated for the Department of State may not be obligated or expended for a capital project described in subsection (b) unless the Secretary of State, in consultation with the Chief of Mission in the country in which the project will be carried out, completes an assessment on the necessity and sustainability of the project; and
(C)
amounts authorized to be appropriated for the United States Agency for International Development may not be obligated or expended for a capital project described in subsection (b) unless the Administrator of the United States Agency for International Development, in consultation with the Mission Director and the Chief of Mission in the country in which the project will be carried out, completes an assessment on the necessity and sustainability of the project.
(2)
Elements
Each assessment on a capital project under this subsection shall include, but not be limited to, the following:
(B)
An estimate of the financial and other requirements necessary for the host government to sustain the project on an annual basis after completion of the project.
(C)
An assessment whether the host government has the capacity (in both financial and human resources) to maintain and use the project after completion.
(D)
A description of any arrangements for the sustainment of the project following its completion if the host government lacks the capacity (in financial or human resources) to maintain the project.
(b)
Covered capital projects
(1)
In general
Except as provided in paragraph (2), a capital project described in this subsection is any capital project overseas for an overseas contingency operation for the benefit of a host country and funded by the Department of Defense, the Department of State, or the United States Agency for International Development, as applicable, if the capital project—
(A)
in the case of a project that directly supports building the capacity of indigenous security forces in the host country, has an estimated value in excess of $10,000,000;
(c)
Waiver
The Secretary of Defense, the Secretary of State, or the Administrator of the United States Agency for International Development, as applicable, may waive the limitation in subsection (a) in order to initiate a capital project if such Secretary or the Administrator, as the case may be, determines that the project is in the national security, diplomatic, or humanitarian interests of the United States. In the first report submitted under subsection (d) after any waiver under this subsection, such Secretary or the Administrator shall include a detailed justification of such waiver. Not later than 90 days after issuing a waiver under this subsection, such Secretary or the Administrator shall submit to the appropriate committees of Congress the assessment described in subsection (a) with respect to the capital project concerned.
(d)
Semi-annual reports
(1)
In general
Not later than 30 days after the end of any fiscal-year half-year in which the Secretary of Defense, the Secretary of State, or the Administrator of the United States Agency for International Development conducts an assessment under subsection (a), such Secretary or the Administrator, as the case may be, shall submit to the appropriate committees of Congress a report setting forth each assessment so conducted during such fiscal-year half-year, including the elements of each capital project so assessed specified in subsection (a)(2).
(2)
Additional elements
In addition to the matters provided for in paragraph (1), each report under that paragraph shall include the following:
(A)
For each capital project covered by such report, an evaluation (other than by amount of funds expended) of the effectiveness of such project, including, at a minimum, the following:
(a)
Limitation
(1)
In general
Commencing 60 days after January 2, 2013—
(A)
amounts authorized to be appropriated for the Department of Defense may not be obligated or expended for a capital project described in subsection (b) unless the Secretary of Defense, in consultation with the United States commander of military operations in the country in which the project will be carried out, completes an assessment on the necessity and sustainability of the project;
(B)
amounts authorized to be appropriated for the Department of State may not be obligated or expended for a capital project described in subsection (b) unless the Secretary of State, in consultation with the Chief of Mission in the country in which the project will be carried out, completes an assessment on the necessity and sustainability of the project; and
(C)
amounts authorized to be appropriated for the United States Agency for International Development may not be obligated or expended for a capital project described in subsection (b) unless the Administrator of the United States Agency for International Development, in consultation with the Mission Director and the Chief of Mission in the country in which the project will be carried out, completes an assessment on the necessity and sustainability of the project.
(2)
Elements
Each assessment on a capital project under this subsection shall include, but not be limited to, the following:
(B)
An estimate of the financial and other requirements necessary for the host government to sustain the project on an annual basis after completion of the project.
(C)
An assessment whether the host government has the capacity (in both financial and human resources) to maintain and use the project after completion.
(D)
A description of any arrangements for the sustainment of the project following its completion if the host government lacks the capacity (in financial or human resources) to maintain the project.
(b)
Covered capital projects
(1)
In general
Except as provided in paragraph (2), a capital project described in this subsection is any capital project overseas for an overseas contingency operation for the benefit of a host country and funded by the Department of Defense, the Department of State, or the United States Agency for International Development, as applicable, if the capital project—
(A)
in the case of a project that directly supports building the capacity of indigenous security forces in the host country, has an estimated value in excess of $10,000,000;
(c)
Waiver
The Secretary of Defense, the Secretary of State, or the Administrator of the United States Agency for International Development, as applicable, may waive the limitation in subsection (a) in order to initiate a capital project if such Secretary or the Administrator, as the case may be, determines that the project is in the national security, diplomatic, or humanitarian interests of the United States. In the first report submitted under subsection (d) after any waiver under this subsection, such Secretary or the Administrator shall include a detailed justification of such waiver. Not later than 90 days after issuing a waiver under this subsection, such Secretary or the Administrator shall submit to the appropriate committees of Congress the assessment described in subsection (a) with respect to the capital project concerned.
(d)
Semi-annual reports
(1)
In general
Not later than 30 days after the end of any fiscal-year half-year in which the Secretary of Defense, the Secretary of State, or the Administrator of the United States Agency for International Development conducts an assessment under subsection (a), such Secretary or the Administrator, as the case may be, shall submit to the appropriate committees of Congress a report setting forth each assessment so conducted during such fiscal-year half-year, including the elements of each capital project so assessed specified in subsection (a)(2).
(2)
Additional elements
In addition to the matters provided for in paragraph (1), each report under that paragraph shall include the following:
(A)
For each capital project covered by such report, an evaluation (other than by amount of funds expended) of the effectiveness of such project, including, at a minimum, the following:
Source
(Pub. L. 112–239, div. A, title XII, § 1273,Jan. 2, 2013, 126 Stat. 2023.)
Codification
Section was enacted as part of the National Defense Authorization Act for Fiscal Year 2013, and not as part of the Foreign Assistance Act of 1961 which comprises this chapter.
The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.
The most recent Classification Table update that we have noticed was Tuesday, May 21, 2013
An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.
| 22 USC | Description of Change | Session Year | Public Law | Statutes at Large |
|---|---|---|---|---|
| § 2421f | new | 2012 | 112-239 [Sec.] 1273 | 126 Stat. 2023 |
LII has no control over and does not endorse any external Internet site that contains links to or references LII.