25 USC § 3506 - Wind and hydropower feasibility study
(a)
Study
The Secretary of Energy, in coordination with the Secretary of the Army and the Secretary, shall conduct a study of the cost and feasibility of developing a demonstration project that uses wind energy generated by Indian tribes and hydropower generated by the Army Corps of Engineers on the Missouri River to supply firming power to the Western Area Power Administration.
(b)
Scope of study
The study shall—
(1)
determine the economic and engineering feasibility of blending wind energy and hydropower generated from the Missouri River dams operated by the Army Corps of Engineers, including an assessment of the costs and benefits of blending wind energy and hydropower compared to current sources used for firming power to the Western Area Power Administration;
(2)
review historical and projected requirements for, patterns of availability and use of, and reasons for historical patterns concerning the availability of firming power;
(3)
assess the wind energy resource potential on tribal land and projected cost savings through a blend of wind and hydropower over a 30-year period;
(4)
determine seasonal capacity needs and associated transmission upgrades for integration of tribal wind generation and identify costs associated with these activities;
(c)
Report
Not later than 1 year after August 8, 2005, the Secretary of Energy, the Secretary, and the Secretary of the Army shall submit to Congress a report that describes the results of the study, including—
(1)
an analysis and comparison of the potential energy cost or benefits to the customers of the Western Area Power Administration through the use of combined wind and hydropower;
(2)
an economic and engineering evaluation of whether a combined wind and hydropower system can reduce reservoir fluctuation, enhance efficient and reliable energy production, and provide Missouri River management flexibility;
(3)
if found feasible, recommendations for a demonstration project to be carried out by the Western Area Power Administration, in partnership with an Indian tribal government or tribal energy resource development organization, and Western Area Power Administration customers to demonstrate the feasibility and potential of using wind energy produced on Indian land to supply firming energy to the Western Area Power Administration; and
prev | next
(a)
Study
The Secretary of Energy, in coordination with the Secretary of the Army and the Secretary, shall conduct a study of the cost and feasibility of developing a demonstration project that uses wind energy generated by Indian tribes and hydropower generated by the Army Corps of Engineers on the Missouri River to supply firming power to the Western Area Power Administration.
(b)
Scope of study
The study shall—
(1)
determine the economic and engineering feasibility of blending wind energy and hydropower generated from the Missouri River dams operated by the Army Corps of Engineers, including an assessment of the costs and benefits of blending wind energy and hydropower compared to current sources used for firming power to the Western Area Power Administration;
(2)
review historical and projected requirements for, patterns of availability and use of, and reasons for historical patterns concerning the availability of firming power;
(3)
assess the wind energy resource potential on tribal land and projected cost savings through a blend of wind and hydropower over a 30-year period;
(4)
determine seasonal capacity needs and associated transmission upgrades for integration of tribal wind generation and identify costs associated with these activities;
(c)
Report
Not later than 1 year after August 8, 2005, the Secretary of Energy, the Secretary, and the Secretary of the Army shall submit to Congress a report that describes the results of the study, including—
(1)
an analysis and comparison of the potential energy cost or benefits to the customers of the Western Area Power Administration through the use of combined wind and hydropower;
(2)
an economic and engineering evaluation of whether a combined wind and hydropower system can reduce reservoir fluctuation, enhance efficient and reliable energy production, and provide Missouri River management flexibility;
(3)
if found feasible, recommendations for a demonstration project to be carried out by the Western Area Power Administration, in partnership with an Indian tribal government or tribal energy resource development organization, and Western Area Power Administration customers to demonstrate the feasibility and potential of using wind energy produced on Indian land to supply firming energy to the Western Area Power Administration; and
Source
(Pub. L. 102–486, title XXVI, § 2606, as added Pub. L. 109–58, title V, § 503(a),Aug. 8, 2005, 119 Stat. 777.)
Prior Provisions
A prior section
3506,Pub. L. 102–486, title XXVI, § 2606,Oct. 24, 1992, 106 Stat. 3118, related to tribal government energy assistance program, prior to the general amendment of this chapter by Pub. L. 109–58.
The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.
The most recent Classification Table update that we have noticed was Monday, June 17, 2013
An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.
| 25 USC | Description of Change | Session Year | Public Law | Statutes at Large |
|---|
LII has no control over and does not endorse any external Internet site that contains links to or references LII.