Upon enactment of legislation to implement an agreement to site a repository negotiated under section
10243(a) of this title, the Secretary shall conduct appropriate site characterization activities for the site that is the subject of such agreement subject to the conditions and terms of such agreement. Any such site characterization activities shall be conducted in accordance with section
10133 of this title, except that references in such section to the Yucca Mountain site and the State of Nevada shall be deemed to refer to the site that is the subject of the agreement and the State or Indian tribe entering into the agreement.
(b) Licensing
(1)Upon the completion of site characterization activities carried out under subsection (a) of this section, the Secretary shall submit to the Nuclear Regulatory Commission an application for construction authorization for a repository at such site.
(2)The Nuclear Regulatory Commission shall consider an application for a construction authorization for a repository or monitored retrievable storage facility in accordance with the laws applicable to such applications, except that the Nuclear Regulatory Commission shall issue a final decision approving or disapproving the issuance of a construction authorization not later than 3 years after the date of the submission of such application.
Upon enactment of legislation to implement an agreement to site a repository negotiated under section
10243(a) of this title, the Secretary shall conduct appropriate site characterization activities for the site that is the subject of such agreement subject to the conditions and terms of such agreement. Any such site characterization activities shall be conducted in accordance with section
10133 of this title, except that references in such section to the Yucca Mountain site and the State of Nevada shall be deemed to refer to the site that is the subject of the agreement and the State or Indian tribe entering into the agreement.
(b) Licensing
(1)Upon the completion of site characterization activities carried out under subsection (a) of this section, the Secretary shall submit to the Nuclear Regulatory Commission an application for construction authorization for a repository at such site.
(2)The Nuclear Regulatory Commission shall consider an application for a construction authorization for a repository or monitored retrievable storage facility in accordance with the laws applicable to such applications, except that the Nuclear Regulatory Commission shall issue a final decision approving or disapproving the issuance of a construction authorization not later than 3 years after the date of the submission of such application.
The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.
The most recent Classification Table update that we have noticed was Wednesday, May 29, 2013
An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.
42 USC
Description of Change
Session Year
Public Law
Statutes at Large
This is a list of parts within the Code of Federal Regulations for which this US Code section provides rulemaking authority.
It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.
LII has no control over and does not endorse any external Internet site that contains links to or references LII.