42 U.S. Code § 16441 - Funding new interconnection and transmission upgrades

prev | next
The Commission may approve a participant funding plan that allocates costs related to transmission upgrades or new generator interconnection, without regard to whether an applicant is a member of a Commission-approved Transmission Organization, if the plan results in rates that—
(1) are just and reasonable;
(2) are not unduly discriminatory or preferential; and
(3) are otherwise consistent with sections 824d and 824e of title 16.

Source

(Pub. L. 109–58, title XII, § 1242,Aug. 8, 2005, 119 Stat. 962.)

This is a list of parts within the Code of Federal Regulations for which this US Code section provides rulemaking authority.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


18 CFR - Conservation of Power and Water Resources

18 CFR Part 385 - RULES OF PRACTICE AND PROCEDURE

 

LII has no control over and does not endorse any external Internet site that contains links to or references LII.