There are authorized to be appropriated such sums as may be necessary to carry out the purposes and provisions of sections
390h through
390h–12p of this title.
(b) Prerequisite cost-sharing agreement
(1)Funds may not be appropriated for the construction of any project authorized by sections
390h to
390h–39 of this title until after—
(A)an appraisal investigation and a feasibility study that complies with the provisions of sections
390h–1(b) or
390h–2(c) of this title, as the case may be, have been completed by the Secretary or the non-Federal project sponsor;
(B)the Secretary has determined that the non-Federal project sponsor is financially capable of funding the non-Federal share of the project’s costs; and
(C)the Secretary has approved a cost-sharing agreement with the non-Federal project sponsor which commits the non-Federal project sponsor to funding its proportionate share of the project’s construction costs on an annual basis.
(2)The requirements of paragraph (1) shall not apply to those projects authorized by sections
390h to
390h–39 of this title for which funds were appropriated prior to January 1, 1996.
(c) Congressional notification
The Secretary shall notify the Committees on Resources and Appropriations of the House of Representatives and the Committees on Energy and Natural Resources and Appropriations of the Senate within 30 days after the signing of a cost-sharing agreement pursuant to subsection (b) of this section that such an agreement has been signed and that the Secretary has determined that the non-Federal project sponsor is financially capable of funding the project’s non-Federal share of the project’s costs.
(d) Ceiling on Federal share
(1)Notwithstanding any other provision of sections
390h to
390h–39 of this title and except as provided by paragraph (2), the Federal share of the costs of each of the individual projects authorized by sections
390h to
390h–39 of this title shall not exceed $20,000,000 (October 1996 prices).
(2)
(A)Subject to subparagraph (B), in the case of any project authorized by sections
390h to
390h–39 of this title for which construction funds were appropriated before January 1, 1996, the Federal share of the cost of such project may not exceed the amount specified as the “total Federal obligation” for that project in the budget justification made by the Bureau of Reclamation for fiscal year 1997, as contained in part 3 of the report of the hearing held on March 27, 1996, before the Subcommittee on Energy and Water Development of the Committee on Appropriations of the House of Representatives.
(B)In the case of the San Gabriel Basin demonstration project authorized by section
390h–12 of this title, the Federal share of the cost of such project may not exceed the sum determined by adding—
(i)the amount that applies to that project under subparagraph (A); and
There are authorized to be appropriated such sums as may be necessary to carry out the purposes and provisions of sections
390h through
390h–12p of this title.
(b) Prerequisite cost-sharing agreement
(1)Funds may not be appropriated for the construction of any project authorized by sections
390h to
390h–39 of this title until after—
(A)an appraisal investigation and a feasibility study that complies with the provisions of sections
390h–1(b) or
390h–2(c) of this title, as the case may be, have been completed by the Secretary or the non-Federal project sponsor;
(B)the Secretary has determined that the non-Federal project sponsor is financially capable of funding the non-Federal share of the project’s costs; and
(C)the Secretary has approved a cost-sharing agreement with the non-Federal project sponsor which commits the non-Federal project sponsor to funding its proportionate share of the project’s construction costs on an annual basis.
(2)The requirements of paragraph (1) shall not apply to those projects authorized by sections
390h to
390h–39 of this title for which funds were appropriated prior to January 1, 1996.
(c) Congressional notification
The Secretary shall notify the Committees on Resources and Appropriations of the House of Representatives and the Committees on Energy and Natural Resources and Appropriations of the Senate within 30 days after the signing of a cost-sharing agreement pursuant to subsection (b) of this section that such an agreement has been signed and that the Secretary has determined that the non-Federal project sponsor is financially capable of funding the project’s non-Federal share of the project’s costs.
(d) Ceiling on Federal share
(1)Notwithstanding any other provision of sections
390h to
390h–39 of this title and except as provided by paragraph (2), the Federal share of the costs of each of the individual projects authorized by sections
390h to
390h–39 of this title shall not exceed $20,000,000 (October 1996 prices).
(2)
(A)Subject to subparagraph (B), in the case of any project authorized by sections
390h to
390h–39 of this title for which construction funds were appropriated before January 1, 1996, the Federal share of the cost of such project may not exceed the amount specified as the “total Federal obligation” for that project in the budget justification made by the Bureau of Reclamation for fiscal year 1997, as contained in part 3 of the report of the hearing held on March 27, 1996, before the Subcommittee on Energy and Water Development of the Committee on Appropriations of the House of Representatives.
(B)In the case of the San Gabriel Basin demonstration project authorized by section
390h–12 of this title, the Federal share of the cost of such project may not exceed the sum determined by adding—
(i)the amount that applies to that project under subparagraph (A); and
Sections
390h through
390h–12p of this title, referred to in subsec. (a), was in the original “sections
1601 through
1630 of this title” meaning sections 1601 through 1630 of title XVI of Pub. L. 102–575, which are classified to sections
390h to
390h–12p of this title and provisions set out as a note under section
390h of this title.
Amendments
2004—Subsec. (d)(2). Pub. L. 108–418designated existing provisions as subpar. (A), substituted “Subject to subparagraph (B), in the case” for “In the case”, and added subpar. (B).
1996—Pub. L. 104–266designated existing provisions as subsec. (a), substituted “300h–12p” for “300h–12”, and added subsecs. (b) to (d).
Change of Name
Committee on Resources of House of Representatives changed to Committee on Natural Resources of House of Representatives by House Resolution No. 6, One Hundred Tenth Congress, Jan. 5, 2007.
The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.
The most recent Classification Table update that we have noticed was Tuesday, May 21, 2013
An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.
43 USC
Description of Change
Session Year
Public Law
Statutes at Large
This is a list of parts within the Code of Federal Regulations for which this US Code section provides rulemaking authority.
It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.