49 USC § 5328 - Project review
Section, Pub. L. 103–272, § 1(d),July 5, 1994, 108 Stat. 828; Pub. L. 104–205, title III, § 336,Sept. 30, 1996, 110 Stat. 2974; Pub. L. 104–287, § 5(9),Oct. 11, 1996, 110 Stat. 3389; Pub. L. 105–178, title III, § 3009(h)(2), (3)(B), (C),June 9, 1998, 112 Stat. 356; Pub. L. 105–206, title IX, § 9009(h)(2), (3),July 22, 1998, 112 Stat. 856; Pub. L. 109–59, title III, § 3027,Aug. 10, 2005, 119 Stat. 1623, related to project review and advancement by the Secretary.
(a)
Schedule.—
(1)
Alternatives analysis.—
The Secretary shall cooperate with an applicant undertaking an alternatives analysis required by subsections (d) and (e) ofsection
5309 in the alternatives analysis and in preparing a draft environmental impact statement and shall approve the draft for circulation not later than 45 days after the applicant submits the draft to the Secretary.
(2)
Advancement to preliminary engineering stage.—
After the draft is circulated and not later than 30 days after the applicant selects a locally preferred alternative, the Secretary shall allow the project to advance to the preliminary engineering stage if the Secretary finds the project meets the requirements of subsection (d) or (e) ofsection
5309.
(3)
Record of decision.—
The Secretary shall issue a record of decision and allow a project to advance to the final design stage not later than 120 days after the final environmental impact statement for the project is completed if the Secretary determines that the project meets the requirements of subsection (d) or (e) ofsection
5309.
(4)
Funding agreements.—
The Secretary shall enter into a full funding grant agreement or project construction grant agreement, as appropriate, between the Government and the project sponsor if the Secretary determines that the project meets the requirements of subsection (d) or (e) ofsection
5309.
(b)
Allowed Delays.—
(1)
Advancement of a project under the time requirements of subsection (a) of this section may be delayed only—
(2)
Not more than 10 days after imposing a delay under paragraph (1)(B) of this subsection, the Secretary shall give the applicant a written statement explaining the reasons for the delay and describing actions the applicant must take to end the delay.
(3)
At least once every 6 months, the Secretary shall report to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Banking, Housing, and Urban Affairs of the Senate on each situation in which the Secretary has not met a time requirement of subsection (a) of this section or delayed a time requirement under paragraph (1)(B) of this subsection. The report shall explain the reasons for the delay and include a plan for achieving timely completion of the Secretary’s review.
(c)
Program of Interrelated Projects.—
(1)
In this subsection, a program of interrelated projects includes the following:
(A)
the New Jersey Urban Core Project (as defined in title III of the Intermodal Surface Transportation Efficiency Act of 1991 (Public Law 102–240, 105 Stat. 2087)).
(B)
the San Francisco Bay Area Rail Extension Program, consisting of at least an extension of the San Francisco Bay Area Rapid Transit District to the San Francisco International Airport (Phase 1a to Colma and Phase 1b to San Francisco Airport), the Santa Clara County Transit District Tasman Corridor Project, a program element designated by a change to the Metropolitan Transportation Commission Resolution No. 1876, and a program element financed completely with non-Government amounts, including the BART Warm Springs Extension, Dublin Extension, and West Pittsburg Extension.
(C)
the Los Angeles Metro Rail Minimum Operable Segment-3 Program, consisting of 7 stations and approximately 11.6 miles of heavy rail subway on the following lines:
(i)
one line running west and northwest from the Hollywood/Vine station to the North Hollywood station, with 2 intermediate stations.
(D)
the Baltimore-Washington Transportation Improvement Program, consisting of 3 extensions of the Baltimore Light Rail to Hunt Valley, Penn Station, and Baltimore-Washington Airport, MARC extensions to Frederick and Waldorf, Maryland, and an extension of the Washington Subway system to Largo, Maryland.
(E)
the Tri-County Metropolitan Transportation District of Oregon Light Rail Program, consisting of the locally preferred alternative for the Westside Light Rail Project, including system related costs, contained in the Department of Transportation and Related Agencies Appropriations Act, 1991 (Public Law 101–516, 104 Stat. 2155), and defined in House Report 101–584, the Hillsboro extension to the Westside Light Rail Project contained in that Act, and the locally preferred alternative for the South/North Corridor Project.
(F)
the Queens Local/Express Connector Program, consisting of the locally preferred alternative for the connection of the 63d Street tunnel extension to the Queens Boulevard lines, the bell-mouth part of the connector that will allow for future access by commuter rail trains and other subway lines to the 63d Street tunnel extension, planning elements for connecting the upper and lower levels to commuter and subway lines in Long Island City, and planning elements for providing a connector for commuter rail transportation to the East side of Manhattan and subway lines to the proposed Second Avenue subway.
(G)
the Dallas Area Rapid Transit Authority light rail elements of the New System Plan, consisting of the locally preferred alternative for the South Oak Cliff corridor, the South Oak Cliff corridor extension-Camp Wisdom, the West Oak Cliff corridor-Westmoreland, the North Central corridor-Park Lane, the North Central corridor-Richardson, Plano, and Garland extensions, the Pleasant Grove corridor-Buckner, and the Carrollton corridors-Farmers Branch and Las Colinas terminal.
(2)
Consistent with the time requirements of subsection (a) of this section or as otherwise provided by law, the Secretary shall make at least one full financing grant agreement for each program described in paragraph (1) of this subsection. The agreement shall include commitments to advance each of the applicant’s program elements (in the program of interrelated projects) through the appropriate program review stages as provided in subsection (a) or as otherwise provided by law and to provide Government financing for each element. The agreement may be changed to include design and construction of a particular element.
Source
(Pub. L. 103–272, § 1(d),July 5, 1994, 108 Stat. 828; Pub. L. 104–205, title III, § 336,Sept. 30, 1996, 110 Stat. 2974; Pub. L. 104–287, § 5(9),Oct. 11, 1996, 110 Stat. 3389; Pub. L. 105–178, title III, § 3009(h)(2), (3)(B), (C),June 9, 1998, 112 Stat. 356; Pub. L. 105–206, title IX, § 9009(h)(2), (3),July 22, 1998, 112 Stat. 856; Pub. L. 109–59, title III, § 3027,Aug. 10, 2005, 119 Stat. 1623.)
| Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
|---|---|---|
| 5328(a) | 49 App.:1602(a)(6). | July 9, 1964, Pub. L. 88–365, 78 Stat. 302, § 3(a)(6)–(8); added Jan. 6, 1983, Pub. L. 97–424, § 304(b), 96 Stat. 2150; restated Dec. 18, 1991, Pub. L. 102–240, § 3011(a), 105 Stat. 2095. |
| 5328(b) | 49 App.:1602(a)(7). | |
| 5328(c)(1) | 49 App.:1602(a)(8)(C). | |
| 5328(c)(2) | 49 App.:1602(a)(8)(A) (1st–3d sentences). | |
| 5328(c)(3) | 49 App.:1602(a)(8)(B). | |
| 5328(c)(4) | 49 App.:1602(a)(8)(A) (last sentence). |
In subsection (a)(1), the words “the date on which” are omitted as surplus.
In subsection (a)(2), the words “the criteria set forth in” are omitted as surplus.
In subsection (a)(4), the words “negotiate and” are omitted as surplus. The words “under section
5309 of this title” are added for clarity.
In subsection (b)(1)(A), the words “solely at the applicant’s discretion” are omitted as surplus.
In subsection (c)(2), the words “if appropriate” are omitted as surplus.
References in Text
The Intermodal Surface Transportation Efficiency Act of 1991, referred to in subsec. (c)(1)(A), is Pub. L. 102–240, Dec. 18, 1991, 105 Stat. 1914, as amended. Title III of the Act is also known as the Federal Transit Act Amendments of 1991. Provisions defining the New Jersey Urban Core Project are contained in section 3031 of the Act, which is not classified to the Code. For complete classification of this Act to the Code, see Short Title of 1991 Amendment note set out under section
101 of this title and Tables.
The Department of Transportation and Related Agencies Appropriations Act, 1991, referred to in subsec. (c)(1)(E), is Pub. L. 101–516, Nov. 5, 1990, 104 Stat. 2155, as amended. Provisions relating to the Westside Light Rail Program are contained in section 328 of the Act, which is not classified to the Code. For complete classification of this Act to the Code, see Tables.
Amendments
2005—Subsec. (a)(1). Pub. L. 109–59, § 3027(1), inserted heading and substituted “The Secretary shall cooperate with an applicant undertaking an alternatives analysis required by subsections (d) and (e) ofsection
5309 in the alternatives analysis” for “When the Secretary of Transportation allows a new fixed guideway project to advance into the alternatives analysis stage of project review, the Secretary shall cooperate with the applicant in alternatives analysis”.
Subsec. (a)(2). Pub. L. 109–59, § 3027(2), inserted heading and substituted “meets the requirements of subsection (d) or (e) ofsection
5309” for “is consistent with section
5309
(e)”.
Subsec. (a)(3). Pub. L. 109–59, § 3027(3), inserted heading, struck out “of construction” after “stage”, and inserted “if the Secretary determines that the project meets the requirements of subsection (d) or (e) ofsection
5309” before period at end.
Subsec. (a)(4). Pub. L. 109–59, § 3027(4), added par. (4) and struck out former par. (4) which read as follows: “The Secretary shall make a full funding grant agreement under section
5309 of this title for a project not later than 120 days after the project enters the final design stage of construction. The agreement shall provide for a United States Government share of the construction cost at least equal to the Government share estimated in the Secretary’s most recent report required under 5309(o)(1) or an update of the report unless the applicant requests otherwise.”
1998—Subsec. (a)(2). Pub. L. 105–178, § 3009(h)(2), substituted “5309(e)” for “5309(e)(1)–(6) of this title”.
Subsec. (a)(4). Pub. L. 105–178, § 3009(h)(3)(C), as added by Pub. L. 105–206, § 9009(h)(3), substituted “5309(o)(1)” for “section
5309
(m)(2) of this title”.
Pub. L. 105–178, § 3009(h)(3)(B), as amended by Pub. L. 105–206, § 9009(h)(2), substituted “full funding” for “full financing”.
1996—Subsec. (b)(3). Pub. L. 104–287substituted “Transportation and Infrastructure” for “Public Works and Transportation”.
Subsec. (c)(1)(E). Pub. L. 104–205struck out “Westside” after “District of Oregon” and “and” after “House Report 101–584,” and inserted before period at end “, and the locally preferred alternative for the South/North Corridor Project”.
Effective Date of 1998 Amendment
Title IX of Pub. L. 105–206effective simultaneously with enactment of Pub. L. 105–178and to be treated as included in Pub. L. 105–178at time of enactment, and provisions of Pub. L. 105–178, as in effect on day before July 22, 1998, that are amended by title IX of Pub. L. 105–206to be treated as not enacted, see section 9016 ofPub. L. 105–206, set out as a note under section
101 of Title
23, Highways.
The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.
The most recent Classification Table update that we have noticed was Wednesday, February 6, 2013
An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.
| 49 USC | Description of Change | Session Year | Public Law | Statutes at Large |
|---|---|---|---|---|
| § 5328 | repealed | 2012 | 112-141 [Sec.] 20002(a) | 126 Stat. 622 |
LII has no control over and does not endorse any external Internet site that contains links to or references LII.