§ 70.74 Additional reporting requirements.
(a) Reports to NRC Operations Center.
(1) Each licensee shall report to the NRC Operations Center the events described in Appendix A toPart 70.
(2) Reports must be made by a knowledgeable licensee representative and by any method that will ensure compliance with the required time period for reporting.
(3) The information provided must include a description of the event and other related information as described in§ 70.50(c)(1).
(4) Follow-up information to the reports must be provided until all information required to be reported in§ 70.50(c)(1) of this subpart is complete.
(5) Each licensee shall provide reasonable assurance that reliable communication with the NRC Operations Center is available during each event.
(b) Written reports. Each licensee that makes a report required by paragraph (a)(1) of this section shall submit a written follow-up report within 30 days of the initial report. The written report must contain the information as described in § 70.50(c)(2).
§ 70.74
Effective Date Note:
At 79 FR 57725, Sept. 26, 2014, § 70.74 was amended by revising paragraph (b), effective Jan. 26, 2014. For the convenience of the user, the revised text is set forth as follows:
§ 70.74 Additional reporting requirements.
(b) Written reports. Each licensee that makes a report required by paragraph (a)(1) of this section shall submit a written follow-up report within 60 days of the initial report. The written report must be sent to the NRC's Document Control Desk, using an appropriate method listed in § 70.5(a), with a copy to the appropriate NRC regional office listed in appendix D to part 20 of this chapter. The reports must include the information as described in § 70.50(c)(2)(i) through (iv).

Title 10 published on 2015-01-01.

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2015-01-05; vol. 80 # 2 - Monday, January 5, 2015
    1. 80 FR 143 - Domestic Licensing of Special Nuclear Material Written Reports and Clarifying Amendments
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Direct final rule; confirmation of effective date.
      The effective date of January 26, 2015, for the direct final rule published September 26, 2014 (79 FR 57721), is confirmed.
      10 CFR Part 70

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Statutes at Large

Title 10 published on 2015-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR Part 70 after this date.

  • 2015-03-17; vol. 80 # 51 - Tuesday, March 17, 2015
    1. 80 FR 13794 - Requirement To Submit Complete and Accurate Information
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Petition for rulemaking; consideration in the rulemaking process.
      The docket for the petition for rulemaking, PRM-50-107, is closed on March 17, 2015.
      10 CFR Parts 30, 40, 50, 52, 60, 61, 63, 70, 71, and 72