§ 900.1 Purpose.

This part provides a process for the timely coordination of information needed for Federal authorizations for proposed electric transmission facilities pursuant to section 216(h) of the Federal Power Act (FPA) ( 16 U.S.C. 824p(h)). This part seeks to ensure electric transmission projects are consistent with the nation's environmental laws, including laws that protect endangered and threatened species, critical habitats and historic properties. This part provides a framework called the Integrated Interagency Pre-Application (IIP) Process by which the U.S. Department of Energy (DOE) cooperates with applicable Federal and Non-Federal entities for the purpose of early coordination and information sharing for permitting and environmental reviews required under Federal law to site qualified electric transmission facilities prior to submission of required Federal request(s). The IIP Process provides for timely and focused pre-application meetings with key Federal and Non-Federal entities, as well as for early identification of potential siting constraints or opportunities, and seeks to promote thorough and consistent stakeholder outreach or engagement by a project proponent during its transmission line planning efforts. The IIP Process occurs before any application or request for authorization is submitted to Federal entities. This part improves the siting process by facilitating the early submission, compilation, and documentation of information needed for subsequent coordinated environmental review of a qualifying project or approved other project by Federal entities under the National Environmental Policy Act (NEPA) following the submission of an application or request for authorization. This part also provides an opportunity for Non-Federal entities to coordinate their non-Federal permitting and environmental reviews with the reviews of the Federal entities.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 10 published on 2015-12-04

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR Part 900 after this date.

  • 2016-09-28; vol. 81 # 188 - Wednesday, September 28, 2016
    1. 81 FR 66500 - Coordination of Federal Authorizations for Electric Transmission Facilities
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Office of Electricity Delivery and Energy Reliability
      Final rule.
      This final rule will become effective November 28, 2016. This rule contains a collection of information requirement subject to OMB approval under the Paperwork Reduction Act. DOE has submitted the collection to OMB for approval and will provide separate notice in the Federal Register of OMB approval and the OMB control number.
      10 CFR Part 900

Title 10 published on 2015-12-04.

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2016-09-28; vol. 81 # 188 - Wednesday, September 28, 2016
    1. 81 FR 66500 - Coordination of Federal Authorizations for Electric Transmission Facilities
      GPO FDSys: XML | Text
      DEPARTMENT OF ENERGY, Office of Electricity Delivery and Energy Reliability
      Final rule.
      This final rule will become effective November 28, 2016. This rule contains a collection of information requirement subject to OMB approval under the Paperwork Reduction Act. DOE has submitted the collection to OMB for approval and will provide separate notice in the Federal Register of OMB approval and the OMB control number.
      10 CFR Part 900