§ 900.5 Selection of the NEPA lead agency.

DOE, in consultation with the Federal entities, shall coordinate the selection of a potential NEPA Lead Agency responsible for preparing an environmental review document under NEPA for proposed qualifying projects. Determination and responsibilities of the NEPA Lead Agency for preparing the EIS shall be in compliance with applicable law, including the National Environmental Policy Act of 1969 and CEQ implementing regulations at 40 CFR part 1500, and each agency's respective NEPA implementing regulations and procedures. However:

(a) For proposed qualifying projects that cross lands administered by both DOI and USDA, DOI and USDA shall consult and jointly determine within thirty (30) calendar days of receiving the initiation request information from DOE which Department has a greater land management interest in the proposed qualifying project and which Department should therefore assume the role of NEPA Lead Agency.

(b) DOI and USDA shall notify DOE of their determination regarding the NEPA Lead Agency in writing within thirty (30) calendar days of making the determination.

(c) Unless DOE notifies DOI and USDA in writing of its objection to that determination within ten (10) calendar days of the DOI/USDA notification, the determination shall be deemed accepted and final. In deciding whether to object to the determination, DOE shall consider the CEQ regulations pertaining to selection of the Lead Agency, including 40 CFR 1501.5(c).

(d) For proposed qualifying projects that do not cross lands administered by both DOI and USDA, DOE and the Federal entities that will likely constitute the cooperating agencies for an environmental review document under NEPA, shall consult and jointly recommend a potential NEPA Lead Agency within 45 calendar days of receiving an IIP Process Close-Out Meeting Request. If DOE and the Federal entities are unable to agree on a recommendation for a NEPA Lead Agency, the Federal entities shall request CEQ to make a final determination by the Close-Out Meeting. No determination of a Federal entity as the potential NEPA Lead Agency under this part shall be made absent that Federal entity's consent.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 10 published on 2015-12-04

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR Part 900 after this date.

  • 2016-09-28; vol. 81 # 188 - Wednesday, September 28, 2016
    1. 81 FR 66500 - Coordination of Federal Authorizations for Electric Transmission Facilities
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Office of Electricity Delivery and Energy Reliability
      Final rule.
      This final rule will become effective November 28, 2016. This rule contains a collection of information requirement subject to OMB approval under the Paperwork Reduction Act. DOE has submitted the collection to OMB for approval and will provide separate notice in the Federal Register of OMB approval and the OMB control number.
      10 CFR Part 900
The section you are viewing is cited by the following CFR sections.

Title 10 published on 2015-12-04.

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2016-09-28; vol. 81 # 188 - Wednesday, September 28, 2016
    1. 81 FR 66500 - Coordination of Federal Authorizations for Electric Transmission Facilities
      GPO FDSys: XML | Text
      DEPARTMENT OF ENERGY, Office of Electricity Delivery and Energy Reliability
      Final rule.
      This final rule will become effective November 28, 2016. This rule contains a collection of information requirement subject to OMB approval under the Paperwork Reduction Act. DOE has submitted the collection to OMB for approval and will provide separate notice in the Federal Register of OMB approval and the OMB control number.
      10 CFR Part 900