Appendix G to Part 73—Reportable Safeguards Events
Pursuant to the provisions of 10 CFR 73.71 (b) and (c), licensees subject to the provisions of 10 CFR 73.20, 73.37, 73.50, 73.55, 73.60, and 73.67 shall report or record, as appropriate, the following safeguards events.
I. Events to be reported within one hour of discovery, followed by a written report within 60 days.
(a) Any event in which there is reason to believe that a person has commited or caused, or attempted to commit or cause, or has made a credible threat to commit or cause:
(1) A theft or unlawful diversion of special nuclear material; or
(2) Significant physical damage to a power reactor or any facility possessing SSNM or its equipment or carrier equipment transporting nuclear fuel or spent nuclear fuel, or to the nuclear fuel or spent nuclear fuel a facility or carrier possesses; or
(3) Interruption of normal operation of a licensed nuclear power reactor through the unauthorized use of or tampering with its machinery, components, or controls including the security system.
(b) An actual entry of an unauthorized person into a protected area, material access area, controlled access area, vital area, or transport.
(c) Any failure, degradation, or the discovered vulnerability in a safeguard system that could allow unauthorized or undetected access to a protected area, material access area, controlled access area, vital area, or transport for which compensatory measures have not been employed.
(d) The actual or attempted introduction of contraband into a protected area, material access area, vital area, or transport.
II. Events to be recorded within 24 hours of discovery in the safeguards event log.
(a) Any failure, degradation, or discovered vulnerability in a safeguards system that could have allowed unauthorized or undetected access to a protected area, material access area, controlled access area, vital area, or transport had compensatory measures not been established.
(b) Any other threatened, attempted, or committed act not previously defined in appendix G with the potential for reducing the effectiveness of the safeguards system below that committed to in a licensed physical security or contingency plan or the actual condition of such reduction in effectiveness.
[52 FR 21658, June 9, 1987, as amended at 60 FR 13618, Mar. 14, 1995; 68 FR 33617, June 5, 2003]

Title 10 published on 2015-01-01.

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2015-01-26; vol. 80 # 16 - Monday, January 26, 2015
    1. 80 FR 3865 - Safeguards Information—Modified Handling Categorization; Change for Materials Facilities
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Direct final rule; confirmation of effective date, NUREG issuance, and correction.
      Effective date: The effective date of January 28, 2015, for the direct final rule published September 30, 2014 (79 FR 58664), is confirmed. The correction of the “Compatibility Table for Direct Final Rule” is effective January 26, 2015.
      10 CFR Parts 30, 37, 73, and 150

Title 10 published on 2015-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR Part 73 after this date.

  • 2015-04-22; vol. 80 # 77 - Wednesday, April 22, 2015
    1. 80 FR 22434 - Enhanced Security of Special Nuclear Material
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Regulatory basis.
      At this time, the NRC is not soliciting public comments on this document. There will be an opportunity for formal public comment on the proposed rule when it is published in the Federal Register .
      10 CFR Part 73