13 CFR § 121.1203 - When will a waiver of the Nonmanufacturer Rule be granted for an individual contract?

§ 121.1203 When will a waiver of the Nonmanufacturer Rule be granted for an individual contract?

(a) Where appropriate, SBA will generally grant waivers for an individual contract or order prior to the issuance of a solicitation, or, where a solicitation has been issued, when the contracting officer provides all potential offerors additional time to respond.

(b) SBA may grant a waiver after contract award, where the contracting officer has determined that the modification is within the scope of the contract and the agency followed the regulations prior to issuance of the solicitation and properly and timely requested a waiver for any other items under the contract, where required.

Example to paragraph (b):
The Government seeks to buy spare parts to fix Item A. After conducting market research, the government determines that Items B, C, and D that are being procured may be eligible for waivers and requests and receives waivers from SBA for those items prior to issuing the solicitation. After the contract is awarded, the Government determines that it will need additional spare parts to fix Item A. The Government determines that adding the additional parts as a modification to the original contract is within scope. The contracting officer believes that one of the additional parts is also eligible for a waiver from SBA, and requests the waiver at the time of the modification. If all other criteria are met, SBA would grant the waiver, even though the contract has already been awarded.

(c) An individual waiver for an item in a solicitation will be approved when the SBA Director, Office of Government Contracting, reviews and accepts a contracting officer's determination that no small business manufacturer or processor can reasonably be expected to offer a product meeting the specifications of a solicitation, including the period of performance.

(d) An individual waiver applies only to the contract for which it is granted and does not apply to modifications outside the scope of the contract or other procurement actions (e.g., follow-on or bridge contracts).

(e) An individual waiver in connection with a long-term contract (i.e., a contract with a duration of longer than five years, including options) cannot exceed five years. A procuring agency may seek a new waiver for an additional five years if, after conducting market research, it demonstrates that there are no available small business manufacturers and that a waiver remains appropriate.

(f) For a multiple item procurement, except those described in § 121.406(d)(1), a waiver must be sought and granted for each item that the procuring agency believes no small business manufacturer or processor can reasonably be expected to offer a product meeting the specifications of the solicitation and which will bring the total value of items to be procured from small business or subject to a waiver to at least 50% of the estimated value of the contract.

(1) SBA's waiver applies only to the specific item(s) identified, not to the entire contract.

(2) The estimated aggregate value of all items manufactured by small business and those subject to a waiver must equal at least 50% of the value of the contract. A contracting officer need not seek a waiver for each item for which the procuring agency believes no small business manufacturer or processor can reasonably be expected to offer a product meeting the specifications of the solicitation.

(3) When a contracting officer seeks a waiver for an individual item, the term “item” can be a specific broad identifying thing (e.g., all spare parts related to aircraft X), but cannot be so broad as to have no real identification (e.g., all medical supplies).

(g) Waivers for the purchase of software.

(1) SBA may grant an individual waiver for the procurement of software provided that the software being sought is an item that is of a type customarily used by the general public or by non-governmental entities for purposes other than governmental purposes, and the item:

(i) Has been sold, leased, or licensed to the general public, or has been offered for sale, lease, or license to the general public;

(ii) Is sold in substantial quantities in the commercial marketplace; and

(iii) Is offered to the Government, without modification, in the same form in which it is sold in the commercial marketplace.

(2) If the value of services provided related to the purchase of a supply item that meets the requirements of paragraph (d)(1) of this section exceeds the value of the item itself, the procurement should be identified as a service procurement, even if the services are provided as part of the same license, lease, or sale terms. If a contracting officer cannot make a determination of the value of services being provided, SBA will assume that the value of the services is greater than the value of items or supplies, and will not grant a waiver.

(3) Subscription services, remote hosting of software, data, or other applications on servers or networks of a party other than the U.S. Government are considered by SBA to be services and not the procurement of a supply item. Therefore SBA will not grant waivers of the nonmanufacturer rule for these types of services.

[81 FR 34260, May 31, 2016, as amended at 88 FR 26203, Apr. 27, 2023]