16 CFR 1.85 - Final environmental impact statements.

§ 1.85 Final environmental impact statements.
(a) After the close of the comment period, the Bureau responsible for the matter will consider the comments received on the draft environmental impact statement and will put the draft statement into final form in accordance with the requirements of CEQ Regulation (40 CFR 1502.9(b)), attaching the comments received (or summaries if response was exceptionally voluminous).
(b) Upon Bureau approval of the final environmental impact statement the final statement will be
(1) Filed with the EPA;
(2) Forwarded to all parties which commented on the draft environmental impact statement and to other interested parties, if practicable;
(3) Placed in the public record of the proposed rule or guide proceeding or legislative matter to which it pertains;
(4) Distributed in any other way which the Bureau in consultation with CEQ deems appropriate.
(c) In rule and guide proceedings, at least thirty (30) days will be allowed for comment on the final environmental impact statement, calculated from the date of publication in the EPA's weekly Federal Register list of final environmental impact statements. In no event will a final rule or guide be promulgated prior to ninety (90) days after notice of the draft environmental impact statement, except where emergency action makes such time period impossible.
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 1.85 Final environmental impact statements.

(a) After the close of the comment period, the Bureau responsible for the matter will consider the comments received on the draft environmental impact statement and will put the draft statement into final form in accordance with the requirements of CEQ Regulation (40 CFR 1502.9(b)), attaching the comments received (or summaries if response was exceptionally voluminous).

(b) Upon Bureau approval of the final environmental impact statement the final statement will be

(1) Filed with the EPA;

(2) Forwarded to all parties which commented on the draft environmental impact statement and to other interested parties, if practicable;

(3) Placed in the public record of the proposed rule or guide proceeding or legislative matter to which it pertains;

(4) Distributed in any other way which the Bureau in consultation with CEQ deems appropriate.

(c) In rule and guide proceedings, at least thirty (30) days will be allowed for comment on the final environmental impact statement, calculated from the date of publication in the EPA's weekly Federal Register list of final environmental impact statements. In no event will a final rule or guide be promulgated prior to ninety (90) days after notice of the draft environmental impact statement, except where emergency action makes such time period impossible.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 5 - GOVERNMENT ORGANIZATION AND EMPLOYEES
U.S. Code: Title 15 - COMMERCE AND TRADE
U.S. Code: Title 26 - INTERNAL REVENUE CODE
U.S. Code: Title 28 - JUDICIARY AND JUDICIAL PROCEDURE
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE
U.S. Code: Title 44 - PUBLIC PRINTING AND DOCUMENTS