18 CFR 157.207 - General reporting requirements.

Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 157.207 General reporting requirements.

On or before May 1, or each year, or in the case of emergency reconstruction activity, prior to any activity, the certificate holder must file, in the manner prescribed in §§ 157.6(a) and 385.2011 of this chapter, an annual report signed under oath by a senior official of the company, that lists for the previous calendar year:

(a) For each new facility authorized by §§ 157.208, 157.210, 157.212, or 157.213, the information specified in § 157.208(e);

(b) For each delivery point authorized under § 157.211(a)(1), the information required by § 157.211(c);

(c) for each temporary compressor facility under § 157.209, the information required by § 157.209(b);

(d) For each storage project tested or developed under § 157.215, the information specified in § 157.215(b)(1);

(e) For each abandonment authorized under § 157.216(a), the information specified in § 157.216(d);

(f) For each change in rate schedule authorized under § 157.217, the information specified in § 157.217(b);

(g) For each change in customer name authorized under § 157.218, the information specified in § 157.218(b); and

(h) If any activity required to be reported under this section was not undertaken, a statement to that effect.

[Order 436, 50 FR 42490, Oct. 18, 1985, as amended by Order 493, 53 FR 15030, Apr. 27, 1988; Order 603, 64 FR 26607, May 14, 1999; Order 603, 66 FR 15347, Mar. 19, 2001; Order 633, 68 FR 31605, May 28, 2003; Order 686, 71 FR 63693, Oct. 31, 2006; Order 686-A, 72 FR 37436, July 10, 2007]

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.

United States Code

Title 18 published on 2015-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR Part 157 after this date.

  • 2015-11-02; vol. 80 # 211 - Monday, November 2, 2015
    1. 80 FR 67302 - Standards for Business Practices of Interstate Natural Gas Pipelines; Coordination of the Scheduling Processes of Interstate Natural Gas Pipelines and Public Utilities
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      This rule will become effective December 2, 2015. Implementation of these standards is required on April 1, 2016. The incorporation by reference of certain publications listed in this rule is approved by the Director of the Federal Register as of December 2, 2015.
      18 CFR Parts 157, 260, and 284