§ 84.86 Termination and enforcement.
(a) Termination.
(1) Awards may be terminated in whole or in part only if paragraphs (a)(1)(i), (a)(1)(ii), or (a)(1)(iii) of this section apply.
(i) By HUD, if a recipient materially fails to comply with the terms and conditions of an award.
(ii) By HUD with the consent of the recipient, in which case the two parties shall agree upon the termination conditions, including the effective date and, in the case of partial termination, the portion to be terminated.
(iii) By the recipient upon sending to HUD written notification setting forth the reasons for such termination, the effective date, and, in the case of partial termination, the portion to be terminated. However, if HUD determines in the case of partial termination that the reduced or modified portion of the grant will not accomplish the purposes for which the grant was made, it may terminate the grant in its entirety under either paragraphs (a)(1)(i) or (a)(1)(ii) of this section.
(2) If costs are allowed under an award, the responsibilities of the recipient referred to in § 84.87(a)(1), including those for property management as applicable, shall be considered in the termination of the award, and provision shall be made for continuing responsibilities of the recipient after termination, as appropriate.
(3) If costs are allowed, the cost principles in § 84.27 apply, even though the award was made on a lump-sum basis. Alternatively, a termination settlement may be reached by prorating the grant amount against the percentage of completion or by some other method as determined by the Grant Officer, as long as the method used results in an equitable settlement to both parties.
(b) Enforcement—
(1) Remedies for noncompliance. If a recipient materially fails to comply with the terms and conditions of an award, whether stated in a Federal statute, regulation, assurance, application, or notice of award, HUD may, in addition to imposing any of the special conditions outlined in § 84.14, take one or more of the following actions, as appropriate in the circumstances.
(i) Temporarily withhold cash payments pending correction of the deficiency by the recipient or more severe enforcement action by HUD.
(ii) Wholly or partly suspend or terminate the current award.
(iii) Withhold further awards for the project or program.
(iv) Take other remedies that may be legally available.
(2) Hearings and appeals. In taking an enforcement action, HUD shall provide the recipient an opportunity for hearing, appeal, or other administrative proceeding to which the recipient is entitled under any statute or regulation applicable to the action involved.
(3) Effects of suspension and termination. Costs of a recipient resulting from obligations incurred by the recipient during a suspension or after termination of an award are not allowable unless HUD expressly authorizes them in the notice of suspension or termination or subsequently. Other recipient costs during suspension or after termination which are necessary and not reasonably avoidable are allowable if paragraphs (b)(3)(i) and (b)(3)(ii) of this section apply.
(i) The costs result from obligations which were properly incurred by the recipient before the effective date of suspension or termination, are not in anticipation of it, and in the case of a termination, are noncancellable.
(ii) The costs would be allowable if the award were not suspended or expired normally at the end of the funding period in which the termination takes effect.
(4) Relationship to debarment and suspension. The enforcement remedies identified in this section, including suspension and termination, do not preclude a recipient from being subject to debarment and suspension under HUD's regulations at 2 CFR part 2424 (see § 84.13).
[59 FR 47011, Sept. 13, 1994, as amended at 72 FR 73492, Dec. 27, 2007]

Title 24 published on 2014-04-01

The following are only the Rules published in the Federal Register after the published date of Title 24.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF TRANSPORTATION, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF HEALTH AND HUMAN SERVICES, DEPARTMENT OF LABOR, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, ENVIRONMENTAL PROTECTION AGENCY, NATIONAL ENDOWMENT FOR THE HUMANITIES, DEPARTMENT OF DEFENSE, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

Title 24 published on 2014-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 24 CFR 84 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF TRANSPORTATION, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF HEALTH AND HUMAN SERVICES, DEPARTMENT OF LABOR, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, ENVIRONMENTAL PROTECTION AGENCY, NATIONAL ENDOWMENT FOR THE HUMANITIES, DEPARTMENT OF DEFENSE, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200