§ 170.214 How does award of an emergency/disaster project affect projects on the FPL?
(a) A tribe may submit an emergency/disaster project any time during the fiscal year. BIA considers these projects a priority and funds them as follows:
(1) If a tribe submits a project before the issuance of the FPL and it is determined as eligible for IRRHPP funds, BIA will provide funding before providing funding for the other approved projects on the FPL; or
(2) If a tribe submits a project after the issuance of the FPL and the distribution of the IRRHPP funds, BIA will provide funding when funds provided to the FPL projects is returned to BIA due to their inability to be obligated. (See § 170.212(c).)
(b) If BIA uses funding previously designated for a project on the FPL to fund an emergency/disaster project, the FPL project that lost its funding will move to the top of the FPL for the following year.

Title 25 published on 2014-04-01.

No entries appear in the Federal Register after this date, for 25 CFR Part 170.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 25 published on 2014-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 25 CFR Part 170 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 76192 - Tribal Transportation Program
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Indian Affairs
      Proposed rule.
      Comments on this rule must be received by March 20, 2015. Comments on the information collections contained in this proposed regulation are separate from those on the substance of the rule. Comments on the information collection burden should be received by January 20, 2015 to ensure consideration, but must be received no later than February 17, 2015.
      25 CFR Part 170