25 CFR § 900.249 - What happens if the contractor fails to take corrective action to remedy the contract deficiencies identified in the notice?
§ 900.249 What happens if the contractor fails to take corrective action to remedy the contract deficiencies identified in the notice?
The Secretary shall provide a second written notice by certified mail to the Indian tribes or tribal organizations served by the contract and the contractor that the contract will be rescinded, in whole or in part.