30 CFR 57.6403 - Branch circuits.

§ 57.6403 Branch circuits.
(a) If electric blasting includes the use of branch circuits, each branch shall be equipped with a safety switch or equivalent method to isolate the circuits to be used.
(b) At least one safety switch or equivalent method of protection shall be located outside the blast area and shall be in the open position until persons are withdrawn.
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 57.6403 Branch circuits.

(a) If electric blasting includes the use of branch circuits, each branch shall be equipped with a safety switch or equivalent method to isolate the circuits to be used.

(b) At least one safety switch or equivalent method of protection shall be located outside the blast area and shall be in the open position until persons are withdrawn.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 30 published on 2015-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR Part 57 after this date.

  • 2015-09-02; vol. 80 # 170 - Wednesday, September 2, 2015
    1. 80 FR 52984 - MSHA Headquarters, Pittsburgh Safety and Health Technology Center, and Respirable Dust Processing Laboratory Address Changes
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Mine Safety and Health Administration
      Final rule; technical amendment.
      Effective Date: September 2, 2015.
      30 CFR Parts 7, 18, 44, 46, 48, 49, 56, 57, 70, 71, 72, 74, 75, and 90