§ 784.13 What additional maps and plans must I include in the reclamation plan?

(a) In addition to the maps and plans required under § 783.24 and other provisions of this subchapter, your application must include maps, plans, and cross-sections of the proposed permit area showing -

(1) The lands that you propose to affect throughout the life of the operation, including the sequence and timing of underground mining activities and the sequence and timing of backfilling, grading, and other reclamation activities to be conducted on areas where the operation will disturb the land surface.

(2) Each area of land for which a performance bond or other equivalent guarantee will be posted under part 800 of this chapter.

(3) Any change that the proposed operations will cause in a facility or feature identified under § 783.24 of this chapter.

(4) All buildings, utility corridors, and facilities to be used or constructed within the proposed permit area, with identification of those facilities that you propose to retain as part of the postmining land use.

(5) Each coal storage, cleaning, processing, and loading area and facility.

(6) Each temporary storage area for soil, spoil, coal mine waste, and noncoal mine waste.

(7) Each water diversion, collection, conveyance, treatment, storage and discharge facility to be used, including the location of each point at which water will be discharged from the proposed permit area to a surface-water body and the name of that water body.

(8) Each disposal facility for coal mine waste and noncoal mine waste materials.

(9) Each feature and facility to be constructed to protect or enhance fish, wildlife, and related environmental values.

(10) Each explosive storage and handling facility.

(11) The location of each siltation structure, sedimentation pond, permanent water impoundment, refuse pile, and coal mine waste impoundment for which plans are required by § 784.25 of this part, and the location of each excess spoil fill for which plans are required under § 784.35 of this part.

(12) Each segment of a perennial or intermittent stream that you propose to mine through, bury, or divert.

(13) Each location in which you propose to restore a perennial or intermittent stream or construct a temporary or permanent diversion of a perennial or intermittent stream.

(14) Each streamside vegetative corridor that you propose to establish.

(15) Each segment of a perennial or intermittent stream that you propose to enhance under the plan submitted in accordance with § 784.16 of this part.

(16) The location and geographic coordinates of each monitoring point for groundwater, surface water, and subsidence.

(17) The location and geographic coordinates of each point at which you propose to monitor the biological condition of perennial and intermittent streams.

(b) Except as provided in §§ 784.25(a)(2), 784.25(a)(3), 784.35, 817.74(c), and 817.81(c) of this chapter, maps, plans, and cross-sections required under paragraphs (a)(5), (6), (7), (10), and (11) of this section must be prepared by, or under the direction of, and certified by a qualified, registered, professional engineer, a professional geologist, or, in any state that authorizes land surveyors to prepare and certify such maps, plans, and cross-sections, a qualified, registered, professional, land surveyor, with assistance from experts in related fields such as landscape architecture.

(c) The regulatory authority may require that you submit the materials required by paragraph (a) of this section in a digital format.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 16 - CONSERVATION
U.S. Code: Title 30 - MINERAL LANDS AND MINING

Title 30 published on 2015-10-21

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR Part 784 after this date.

  • 2016-12-20; vol. 81 # 244 - Tuesday, December 20, 2016
    1. 81 FR 93066 - Stream Protection Rule
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Office of Surface Mining Reclamation and Enforcement
      Final rule.
      This rule is effective January 19, 2017.
      30 CFR Parts 700, 701, 773, 774, 777, 779, 780, 783, 784, 785, 800, 816, 817, 824, and 827
The section you are viewing is cited by the following CFR sections.

Title 30 published on 2015-10-21.

The following are only the Rules published in the Federal Register after the published date of Title 30.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2016-12-20; vol. 81 # 244 - Tuesday, December 20, 2016
    1. 81 FR 93066 - Stream Protection Rule
      GPO FDSys: XML | Text
      DEPARTMENT OF THE INTERIOR, Office of Surface Mining Reclamation and Enforcement
      Final rule.
      This rule is effective January 19, 2017.
      30 CFR Parts 700, 701, 773, 774, 777, 779, 780, 783, 784, 785, 800, 816, 817, 824, and 827