§ 154.510 Loading arms.

(a) Each mechanical loading arm used for transferring oil or hazardous material and placed into service after June 30, 1973, must meet the design, fabrication, material, inspection, and testing requirements in ANSI B31.3 (incorporated by reference; see § 154.106).

(b) The manufacturer's certification that the standard in paragraph (a) of this section has been met must be permanently marked on the loading arm or recorded elsewhere at the facility with the loading arm marked to identify it with that information.

(c) Each mechanical loading arm used for transferring oil or hazardous material must have a means of being drained or closed before being disconnected after transfer operations are completed.

[CGD 75-124, 45 FR 7172, Jan. 31, 1980, as amended by CGD 86-034, 55 FR 36253, Sept. 4, 1990; USCG-2001-8661, 74 FR 45022, Aug. 31, 2009]

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Presidential Documents

Executive Order ... 12777

Title 33 published on 2015-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 33 CFR Part 154 after this date.

  • 2015-09-10; vol. 80 # 175 - Thursday, September 10, 2015
    1. 80 FR 54418 - Marine Vapor Control Systems
      GPO FDSys XML | Text
      DEPARTMENT OF HOMELAND SECURITY, Coast Guard
      Final rule; information collection approval.
      The collection of information requirements contained in the July 16, 2013 final rule (78 FR 42596) and approved by the OMB as an amendment to existing collection of information, control number 1625-0060, will be enforced beginning September 10, 2015. The requirements include provisions for VCS certifications, recertifications, periodic operational reviews, approval requests, reviews of operating manuals, failure analyses, operational review letters, and relabeling. These requirements aid the Coast Guard and industry in ensuring industry's regulatory compliance and safe practices in connection with VCSs.
      33 CFR Parts 154, 155, and 156
The section you are viewing is cited by the following CFR sections.