40 CFR 147.3015 - Information to be considered for Class III wells.

§ 147.3015 Information to be considered for Class III wells.

(a) In addition to the requirements of § 146.34(a) of this chapter, the following information shall be considered by the Director:

(1) Proposed construction procedures, including a cementing and casing program, logging procedures, deviation checks, and a drilling, testing and coring program.

(2) Depth to the proposed injection zone, and a chemical, physical and radiological analysis of the ground water in the proposed injection zone sufficient to define pre-injection water quality as required for aquifer cleanup by § 147.3011 of this subpart.

(3) An aquifer cleanup plan if required by § 147.3003(b) of this subpart.

(4) Any additional information that may be necessary to demonstrate that cleanup will reduce the level of contaminants in the surrounding USDWs as close as feasible to the original conditions.

(b) In addition to the requirements of § 146.34(b) of this chapter, the Director shall consider any information required under § 146.34(a) of this chapter (as supplemented by this subpart) that has been gathered during construction.

Title 40 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR Part 147 after this date.

  • 2017-01-26; vol. 82 # 16 - Thursday, January 26, 2017
    1. 82 FR 8499 - Delay of Effective Date for 30 Final Regulations Published by the Environmental Protection Agency Between October 28, 2016 and January 17, 2017
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule; delay of effective dates.
      This regulation is effective January 26, 2017. The effective date of each regulation listed in the table below is delayed to a new effective date of March 21, 2017.
      40 CFR Parts 22, 51, 52, 61, 68, 80, 81, 124, 147, 171, 239, 259, 300, and 770