40 CFR 147.3107 - Mechanical integrity.

§ 147.3107 Mechanical integrity.

(a) Monitoring of annulus pressure conducted pursuant to § 146.8(b)(1) shall be preceded by an initial pressure test. A positive gauge pressure on the casing/tubing annulus (filled with liquid) shall be maintained continuously. The pressure shall be monitored monthly.

(b) Pressure tests conducted pursuant to § 146.8(b)(2) of this chapter shall be performed with a pressure on the casing/tubing annulus of at least 200 p.s.i. unless otherwise specified by the Director. In addition, pressure tests conducted during well operation shall maintain an injection/annulus pressure differential of at least 100 p.s.i. throughout the tubing length.

(c) Monitoring of enhanced recovery wells conducted pursuant to § 146.8(b)(3), must be preceded by an initial pressure test that was conducted no more than 90 days prior to the commencement of monitoring.

Title 40 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR Part 147 after this date.

  • 2017-01-26; vol. 82 # 16 - Thursday, January 26, 2017
    1. 82 FR 8499 - Delay of Effective Date for 30 Final Regulations Published by the Environmental Protection Agency Between October 28, 2016 and January 17, 2017
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule; delay of effective dates.
      This regulation is effective January 26, 2017. The effective date of each regulation listed in the table below is delayed to a new effective date of March 21, 2017.
      40 CFR Parts 22, 51, 52, 61, 68, 80, 81, 124, 147, 171, 239, 259, 300, and 770