40 CFR 63.1090 - What reports must I submit?

Status message

There are 12 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
prev | next
§ 63.1090 What reports must I submit?
If you delay repair for your heat exchange system, you must report the delay of repair in the semiannual report required by § 63.1110(e). If the leak remains unrepaired, you must continue to report the delay of repair in semiannual reports until you repair the leak. You must include the information in paragraphs (a) through (e) of this section in the semiannual report.
(a) The fact that a leak was detected, and the date that the leak was detected.
(b) Whether or not the leak has been repaired.
(c) The reasons for delay of repair. If you delayed the repair as provided in § 63.1088(b), documentation of emissions estimates.
(d) If a leak remains unrepaired, the expected date of repair.
(e) If a leak is repaired, the date the leak was successfully repaired.

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63