§ 63.11087 What requirements must I meet for gasoline storage tanks if my facility is a bulk gasoline terminal, pipeline breakout station, or pipeline pumping station?
(a) You must meet each emission limit and management practice in Table 1 to this subpart that applies to your gasoline storage tank.
(b) You must comply with the requirements of this subpart by the applicable dates specified in § 63.11083, except that storage vessels equipped with floating roofs and not meeting the requirements of paragraph (a) of this section must be in compliance at the first degassing and cleaning activity after January 10, 2011 or by January 10, 2018, whichever is first.
(c) You must comply with the applicable testing and monitoring requirements specified in § 63.11092(e).
(d) You must submit the applicable notifications as required under § 63.11093.
(e) You must keep records and submit reports as specified in §§ 63.11094 and 63.11095.
(f) If your gasoline storage tank is subject to, and complies with, the control requirements of 40 CFR part 60, subpart Kb of this chapter, your storage tank will be deemed in compliance with this section. You must report this determination in the Notification of Compliance Status report under § 63.11093(b).

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63