Table 1 to Subpart GGGGGG of Part 63—Applicability of General Provisions to Primary Zinc Production Area Sources

As required in § 63.11164(a) and (b), you must comply with the requirements of the NESHAP General Provisions (40 CFR part 63, subpart A) as shown in the following table.

Citation Subject Applies to subpart GGGGGG Explanation
63.1(a)(1), (a)(2), (a)(3), (a)(4), (a)(6), (a)(10)–(a)(12), (b)(1), (b)(3), (c)(1), (c)(2), (c)(5), (e) Applicability Yes.
63.1(a)(5), (a)(7)–(a)(9), (b)(2), (c)(3), (c)(4), (d) Reserved No.
63.2 Definitions Yes.
63.3 Units and Abbreviations Yes.
63.4 Prohibited Activities and Circumvention Yes.
63.5 Preconstruction Review and Notification Requirements No.
63.6(a), (b)(1)–(b)(5), (b)(7), (c)(1), (c)(2), (c)(5) Compliance with Standards and Maintenance Requirements—Applicability Compliance Dates Yes.
63.6(e) Operation and Maintenance Requirements Yes/No Operation and maintenance requirements do not apply to existing sources except that the startup, shutdown, and malfunction requirements in § 63.6(e)(3) are allowed as an alternative to the rule requirements for emergency situations. Operation and maintenance requirements apply to new sources except that the rule requirements for emergency situations are allowed as an alternative to the startup, shutdown, and malfunction requirements in § 63.6(e)(3).
63.6(f), (g), (i), (j) Compliance with Nonopacity Emission Standards Yes.
63.6(b)(6), (c)(3), (c)(4), (d), (e)(2), (e)(3)(ii), (h)(3), (h)(5)(iv) Reserved No.
63.6(h)(1)–(h)(4), (h)(5)(i)–(h)(5)(iii), (h)(6)–(h)(9) Yes.
63.7(a), (e), (f), (g), (h) Performance Testing Requirements Yes.
63.7(b), (c) Yes/No Notification of performance tests and quality assurance program apply to new sources but not existing sources.
63.8(a)(1), (a)(2), (b), (c), (f), (g) Monitoring Requirements Yes Requirements in § 63.6(c)(4)(i)–(ii), (c)(5), (c)(6), (d), (e), (f)(6), and (g) apply if a COMS is used.
63.8(a)(3) Reserved No.
63.8(a)(4) No Subpart GGGGGG does not require flares.
63.8(d), (e) Yes/No Requirements for quality control program and performance evaluations apply to new sources but not existing sources.
63.9(a), (b)(1), (b)(2), (b)(5), (c), (d), (f), (g), (h)(1)–(h)(3), (h)(5), (h)(6), (i), (j) Notification Requirements Yes/No Notification of performance tests and opacity or visible emissions observations apply to new sources but not existing sources.
63.9(b)(3), (h)(4) Reserved No.
63.9(b)(4) No.
63.10(a), (b)(1), (b)(2)(i)–(v), (d)(4), (d)(5)(i), (f) Recordkeeping and Reporting Requirements Yes.
63.10(b)(2), (b)(3), (c)(1), (c)(5)–(c)(8), (c)(10)–(c)(15), (d)(1)–(d)(3), (d)(5)(ii), (e)(1), (e)(2), (e)(4) Yes/No Recordkeeping and reporting requirements apply to new sources but not existing sources.
63.10(c)(2)–(c)(4), (c)(9) Reserved No.
63.10(e)(3) Yes/No Reporting requirements apply to new sources but not existing sources.
63.11 Control Device Requirements No Subpart GGGGGG does not require flares.
63.12 State Authorities and Delegations Yes.
63.13 Addresses Yes.
63.14 Incorporations by Reference Yes.
63.15 Availability of Information and Confidentiality Yes.
63.16 Performance Track Provisions Yes.