40 CFR Appendix Table 2 to Subpart IIII of Part 63 - Table 2 to Subpart IIII of Part 63—Applicability of General Provisions to Subpart IIII of Part 63

Table 2 to Subpart IIII of Part 63—Applicability of General Provisions to Subpart IIII of Part 63

You must comply with the applicable General Provisions requirements according to the following table:

Citation Subject Applicable to subpart IIII Explanation
§ 63.1(a)(1)–(12) General Applicability Yes
§ 63.1(b)(1)–(3) Initial Applicability Determination Yes Applicability to subpart IIII is also specified in § 63.3081.
§ 63.1(c)(1) Applicability After Standard Established Yes
§ 63.1(c)(2) Applicability of Permit Program for Area Sources No Area sources are not subject to subpart IIII.
§ 63.1(c)(5) Extensions and Notifications Yes
§ 63.1(c)(6) Reclassification Yes
§ 63.1(e) Applicability of Permit Program Before Relevant Standard is Set Yes
§ 63.2 Definitions Yes Additional definitions are specified in § 63.3176.
§ 63.3 Units and Abbreviations Yes
§ 63.4(a)(1)–(2) Prohibited Activities Yes
§ 63.4(b)–(c) Circumvention/Fragmentation Yes
§ 63.5(a) Preconstruction Review Applicability Yes
§ 63.5(b)(1), (3), (4), (6) Requirements for Existing, Newly Constructed, and Reconstructed Sources Yes
§ 63.5(d)(1)(i)–(ii)(F), (d)(1)(ii)(H), (d)(1)(ii)(J), (d)(1)(iii), (d)(2)–(4) Application for Approval of Construction/Reconstruction Yes
§ 63.5(e) Approval of Construction/Reconstruction Yes
§ 63.5(f) Approval of Construction/Reconstruction Based on Prior State Review Yes
§ 63.6(a) Compliance With Standards and Maintenance Requirements—Applicability Yes
§ 63.6(b)(1)–(5), (b)(7) Compliance Dates for New and Reconstructed Sources Yes Section 63.3083 specifies the compliance dates.
§ 63.6(c)(1), (2), (5) Compliance Dates for Existing Sources Yes Section 63.3083 specifies the compliance dates.
§ 63.6(e)(1)(i)–(ii) Operation and Maintenance Yes before January 5, 2021. No on and after January 5, 2021 See § 63.3100(d) for general duty requirement.
§ 63.6(e)(1)(iii) Operation and Maintenance Yes
§ 63.6(e)(3)(i), (e)(3)(iii)–(ix) SSMP Yes before January 5, 2021. No on and after January 5, 2021
§ 63.6(f)(1) Compliance Except During SSM Yes before January 5, 2021. No on and after January 5, 2021
§ 63.6(f)(2)–(3) Methods for Determining Compliance Yes
§ 63.6(g) Use of an Alternative Standard Yes
§ 63.6(h) Compliance With Opacity/Visible Emission Standards No Subpart IIII does not establish opacity standards and does not require continuous opacity monitoring systems (COMS).
§ 63.6(i)(1)–(14), (16) Extension of Compliance Yes
63.6(j) Presidential Compliance Exemption Yes
§ 63.7(a)(1) Performance Test Requirements—Applicability Yes Applies to all affected sources. Additional requirements for performance testing are specified in §§ 63.3164 and 63.3166.
§ 63.7(a)(2) except (a)(2)(i)–(viii) Performance Test Requirements—Dates Yes Applies only to performance tests for capture system and control device efficiency at sources using these to comply with the standards. Section 63.3160 specifies the schedule for performance test requirements that are earlier than those specified in § 63.7(a)(2).
§ 63.7(a)(3)–(4) Performance Tests Required By the Administrator, Force Majeure Yes
§ 63.7(b)–(d) Performance Test Requirements—Notification, Quality Assurance, Facilities Necessary for Safe Testing Conditions During Test Yes Applies only to performance tests for capture system and add-on control device efficiency at sources using these to comply with the standards.
§ 63.7(e)(1) Conduct of performance tests Yes before January 5, 2021. No on and after January 5, 2021 See § 63.3164.
§ 63.7(e)(2)–(4) Conduct of performance tests Yes
§ 63.7(f) Performance Test Requirements—Use of Alternative Test Method Yes Applies to all test methods except those used to determine capture system efficiency.
§ 63.7(g)–(h) Performance Test Requirements—Data Analysis, Recordkeeping, Reporting, Waiver of Test Yes Applies only to performance tests for capture system and add-on control device efficiency at sources using these to comply with the standards.
§ 63.8(a)(1)–(2) Monitoring Requirements—Applicability Yes Applies only to monitoring of capture system and add-on control device efficiency at sources using these to comply with the standards. Additional requirements for monitoring are specified in § 63.3168.
§ 63.8(a)(4) Additional Monitoring Requirements No Subpart IIII does not have monitoring requirements for flares.
§ 63.8(b) Conduct of Monitoring Yes
§ 63.8(c)(1) Continuous Monitoring Systems (CMS) Operation and Maintenance Yes before January 5, 2021. No on and after January 5, 2021 Section 63.3168 specifies the requirements for the operation of CMS for capture systems and add-on control devices at sources using these to comply.
63.8(c)(2)–(3) CMS Operation and Maintenance Yes Applies only to monitoring of capture system and add-on control device efficiency at sources using these to comply with the standards. Additional requirements for CMS operations and maintenance are specified in § 63.3168.
§ 63.8(c)(4) CMS No Section 63.3168 specifies the requirements for the operation of CMS for capture systems and add-on control devices at sources using these to comply with the standards.
§ 63.8(c)(5) COMS No Subpart IIII does not have opacity or visible emission standards.
§ 63.8(c)(6) CMS Requirements No Section 63.3168 specifies the requirements for monitoring systems for capture systems and add-on control devices at sources using these to comply with the standards.
§ 63.8(c)(7) CMS Out-of-Control Periods Yes
§ 63.8(c)(8) CMS Out-of-Control Periods Reporting No Section 63.3120 requires reporting of CMS out-of-control periods.
§ 63.8(d)–(e) Quality Control Program and CMS Performance Evaluation No Subpart IIII does not require the use of continuous emissions monitoring systems.
§ 63.8(f)(1)–(5) Use of an Alternative Monitoring Method Yes
§ 63.8(f)(6) Alternative to Relative Accuracy Test No Subpart IIII does not require the use of CEMS.
§ 63.8(g) Data Reduction No Sections 63.3167 and 63.3168 specify monitoring data reduction.
§ 63.9(a) Notification Requirements Yes
§ 63.9(b)(1)–(2) Initial Notifications Yes
§ 63.9(b)(4)(i), (b)(4)(v), (b)(5) Application for Approval of Construction or Reconstruction Yes
§ 63.9(c) Request for Extension of Compliance Yes
§ 63.9(d) Special Compliance Requirement Notification Yes
§ 63.9(e) Notification of Performance Test Yes Applies only to capture system and add-on control device performance tests at sources using these to comply with the standards.
§ 63.9(f) Notification of Visible Emissions/Opacity Test No Subpart IIII does not have opacity or visible emission standards.
§ 63.9(g) Additional Notifications When Using CMS No Subpart IIII does not require the use of CEMS.
§ 63.9(h)(1)–(3), (5)–(6) Notification of Compliance Status Yes Section 63.3110 specifies the dates for submitting the notification of compliance status.
§ 63.9(i) Adjustment of Submittal Deadlines Yes
§ 63.9(j) Change in Previous Information Yes
§ 63.9(k) Electronic reporting procedures Yes Only as specified in § 63.9(j).
§ 63.10(a) Recordkeeping/Reporting—Applicability and General Information Yes
§ 63.10(b)(1) General Recordkeeping Requirements Yes Additional requirements are specified in §§ 63.3130 and 63.3131.
§ 63.10(b)(2)(i)–(ii) Recordkeeping of Occurrence and Duration of Startups and Shutdowns and of Failures to Meet Standards Yes before January 5, 2021. No on and after January 5, 2021 See 63.3130(g).
§ 63.10(b)(2)(iii) Recordkeeping Relevant to Maintenance of Air Pollution Control and Monitoring Equipment Yes
§ 63.10(b)(2)(iv)–(v) Actions Taken to Minimize Emissions During SSM Yes before January 5, 2021. No on and after January 5, 2021 See § 63.3130(g)(4) for a record of actions taken to minimize emissions during a deviation from the standard.
§ 63.10(b)(2)(vi) Recordkeeping for CMS Malfunctions Yes before January 5, 2021. No on and after January 5, 2021 See § 63.3130(g) for records of periods of deviation from the standard, including instances where a CMS is inoperative or out-of-control.
§ 63.10(b)(2)(vii)–(xi) Records Yes
§ 63.10(b)(2)(xii) Records Yes
§ 63.10(b)(2)(xiii) No Subpart IIII does not require the use of CEMS.
§ 63.10(b)(2)(xiv) Yes
§ 63.10(b)(3) Recordkeeping Requirements for Applicability Determinations Yes
§ 63.10(c)(1)–(6) Additional Recordkeeping Requirements for Sources with CMS Yes
§ 63.10(c)(7)–(8) Additional Recordkeeping Requirements for Sources with CMS No See § 63.3130(g) for records of periods of deviation from the standard, including instances where a CMS is inoperative or out-of-control.
§ 63.10(c)(10)–(14) Yes
§ 63.10(c)(15) Records Regarding the SSM Plan Yes before January 5, 2021. No on and after January 5, 2021
§ 63.10(d)(1) General Reporting Requirements Yes Additional requirements are specified in § 63.3120.
§ 63.10(d)(2) Report of Performance Test Results Yes Additional requirements are specified in § 63.3120(b).
§ 63.10(d)(3) Reporting Opacity or Visible Emissions Observations No Subpart IIII does not require opacity or visible emissions observations.
§ 63.10(d)(4) Progress Reports for Sources With Compliance Extensions Yes
§ 63.10(d)(5) SSM Reports Yes before January 5, 2021. No on and after January 5, 2021 See 63.3120(a)(6).
§ 63.10(e)(1)–(2) Additional CMS Reports No Subpart IIII does not require the use of CEMS.
§ 63.10(e)(3) Excess Emissions/CMS Performance Reports No Section 63.3120(b) specifies the contents of periodic compliance reports.
§ 63.10(e)(4) COMS Data Reports No Subpart IIII does not specify requirements for opacity or COMS.
§ 63.10(f) Recordkeeping/Reporting Waiver Yes
§ 63.11 Control Device Requirements/Flares No Subpart IIII does not specify use of flares for compliance.
§ 63.12 State Authority and Delegations Yes
§ 63.13 Addresses Yes
§ 63.14 IBR Yes
§ 63.15 Availability of Information/Confidentiality Yes
[85 FR 41133, July 8, 2020, as amended at 85 FR 73904, Nov. 19, 2020]