40 CFR Appendix Table 3 to Subpart GGG of Part 62 - Generic Compliance Schedule and Increments of Progress a
prev | next
Table 3 to Subpart GGG of Part 62—Generic Compliance Schedule and Increments of Progress
a
| Increment | Date |
|---|---|
| Increment 1—Submit final control plan | 1 year after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b |
| Increment 2—Award Contracts | 20 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b |
| Increment 3—Begin on-site construction | 24 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b |
| Increment 4—Complete on-site construction | 30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b |
| Increment 5—Final compliance | 30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b |
a Table 3 of subpart GGG applies to landfills with design capacities ≥2.5 million megagrams and 2.5 million cubic meters that are subject to this subpart except those with site-specific compliance schedules shown in table 4 of subpart GGG.
b NMOC = nonmethane organic compounds Mg/yr = megagrams per year