40 CFR Appendix Table 1 to Subpart FFFF of Part 60 - Table 1 to Subpart FFFF of Part 60—Model Rule—Compliance Schedule

Table 1 to Subpart FFFF of Part 60—Model Rule—Compliance Schedule

As stated in § 60.3000, you must comply with the following:

Complete this action By this date a
Final compliance b (Dates to be specified in State plan) c.

a Site-specific schedules can be used at the discretion of the State.

b Final compliance means that you complete all process changes and retrofit of control devices so that, when the incineration unit is brought on line, all process changes and air pollution control devices necessary to meet the emission limitations operate as designed.

c The date can be no later than 3 years after the effective date of State plan approval or December 16, 2010, whichever is earlier.