40 CFR Appendix Table 3 to Subpart GGG of Part 62 - Table 3 to Subpart GGG of Part 62—Generic Compliance Schedule and Increments of Progress a

prev | next
Table 3 to Subpart GGG of Part 62—Generic Compliance Schedule and Increments of Progress a
Increment Date
Increment 1—Submit final control plan 1 year after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b
Increment 2—Award Contracts 20 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b
Increment 3—Begin on-site construction 24 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b
Increment 4—Complete on-site construction 30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b
Increment 5—Final compliance 30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr. b

a Table 3 of subpart GGG applies to landfills with design capacities ≥2.5 million megagrams and 2.5 million cubic meters that are subject to this subpart except those with site-specific compliance schedules shown in table 4 of subpart GGG.

b NMOC = nonmethane organic compounds Mg/yr = megagrams per year