40 CFR Appendix Table 3 to Subpart F of Part 63 - Table 3 to Subpart F of Part 63—General Provisions Applicability to Subparts F, G, and H a to Subpart F

Table 3 to Subpart F of Part 63—General Provisions Applicability to Subparts F, G, and H a to Subpart F
Reference Applies to subparts F, G, and H Comment
63.1(a)(1) Yes Overlap clarified in § 63.101, § 63.111, § 63.161.
63.1(a)(2) Yes
63.1(a)(3) Yes § 63.110 and § 63.160(b) of subparts G and H identify which standards are overridden.
63.1(a)(4) No Subpart F specifies applicability of each paragraph in subpart A to subparts F, G, and H.
63.1 (a)(5)–(a)(9) No
63.1(a)(10) No Subparts F, G, and H specify calendar or operating day.
63.1(a)(11) No Subpart F § 63.103(d) specifies acceptable methods for submitting reports. a
63.1 (a)(12)–(a)(14) Yes
63.1(b)(1) No Subpart F specifies applicability.
63.1(b)(2) Yes
63.1(b)(3) No
63.1(c)(1) No Subpart F specifies applicability.
63.1(c)(2) No Area sources are not subject to subparts F, G, and H.
63.1(c)(3) No
63.1(c)(4) Yes
63.1(c)(5) No Subparts G and H specify applicable notification requirements.
63.1(c)(6) Yes
63.1(d) No
63.1(e) No Subparts F, G, and H established before permit program.
63.2 Yes Subpart F § 63.101(a) specifies those subpart A definitions that apply to the HON. Subpart F definition of “source” is equivalent to subpart A definition of “affected source.”
63.3 No Units of measure are spelled out in subparts F, G, and H.
63.4 (a)(1)–(a)(3) Yes
63.4(a)(4) No This is a reserved paragraph in subpart A of part 63.
63.4(a)(5) Yes
63.4(b) Yes
63.4(c) Yes
63.5(a)(1) Yes Except the terms “source” and “stationary source” in § 63.5(a)(1) should be interpreted as having the same meaning as “affected source.”
63.5(a)(2) Yes
63.5(b)(1) Yes Except § 63.100(l) defines when construction or reconstruction is subject to standards for new sources.
63.5(b)(2) No This is a reserved paragraph in subpart A of part 63.
63.5(b)(3) Yes
63.5(b)(4) Yes Except the cross reference to § 63.9(b) is limited to § 63.9(b) (4) and (5). Subpart F overrides § 63.9 (b)(1) through (b)(3).
63.5(b)(5) Yes
63.5(b)(6) Yes Except § 63.100(l) defines when construction or reconstruction is subject to standards for new sources.
63.5(c) No This is a reserved paragraph in subpart A of part 63.
63.5(d)(1)(i) No For subpart G, see § 63.151(b) (2)(ii) and (2)(iii) for the applicability and timing of this submittal; for subpart H, see § 63.182(b) (2)(ii) and (b)(2)(iii) for applicability and timing of this submittal.
63.5(d)(1)(ii) Yes Except § 63.5(d)(1)(ii)(H) does not apply.
63.5(d)(1)(iii) No Subpart G requires submittal of the Notification of Compliance Status in § 63.152(b); subpart H specifies requirements in § 63.182(c).
63.5(d)(2) No
63.5(d)(3) Yes—subpart G No—subpart H Except § 63.5(d)(3)(ii) does not apply to subpart G.
63.5(d)(4) Yes
63.5(e) Yes
63.5(f)(1) Yes
63.5(f)(2) Yes Except the cross-reference to § 63.5(d)(1) is changed to § 63.151(b)(2)(ii) of subpart G and to § 63.182(b)(2)(ii) of subpart H. The cross-reference to § 63.5(b)(2) does not apply.
63.6(a) Yes
63.6(b)(1) No Subparts F and H specify compliance dates for sources subject to subparts F, G, and H.
63.6(b)(2) No
63.6(b)(3) Yes
63.6(b)(4) No May apply when standards are proposed under Section 112(f) of the Clean Air Act.
63.6(b)(5) No Subparts G and H include notification requirements.
63.6(b)(6) No
63.6(b)(7) No
63.6(c)(1) No Subpart F specifies the compliance dates for subparts G and H.
63.6(c)(2) No
63.6(c)(3) No
63.6(c)(4) No
63.6(c)(5) Yes
63.6(d) No
63.6(e) Yes Except as otherwise specified for individual paragraphs. Does not apply to Group 2 emission points unless they are included in an emissions average. b
63.6(e)(1)(i) No This is addressed by § 63.102(a)(4) of subpart F.
63.6(e)(1)(ii) Yes
63.6(e)(1)(iii) Yes
63.6(e)(2) Yes
63.6(e)(3)(i) Yes For subpart H, the startup, shutdown, and malfunction plan requirement of § 63.6(e)(3)(i) is limited to control devices subject to the provisions of subpart H and is optional for other equipment subject to subpart H. The startup, shutdown, and malfunction plan may include written procedures that identify conditions that justify a delay of repair.
63.6(e)(3)(i)(A) No This is addressed by § 63.102(a)(4).
63.6(e)(3)(i)(B) Yes
63.6(e)(3)(i)(C) Yes
63.6(e)(3)(ii) Yes
63.6(e)(3)(iii) No Recordkeeping and reporting are specified in § 63.103(c)(2) of subpart F and § 63.152(d)(1) of subpart G.
63.6(e)(3)(iv) No Recordkeeping and reporting are specified in § 63.103(c)(2) of subpart F and § 63.152(d)(1) of subpart G.
63.6(e)(3)(v) No Records retention requirements are specified in § 63.103(c).
63.6(e)(3)(vi) Yes
63.6(e)(3)(vii) Yes
63.6(e)(3)(vii)(A) Yes
63.6(e)(3)(vii)(B) Yes Except the plan must provide for operation in compliance with § 63.102(a)(4).
63.6(e)(3)(vii)(C) Yes
63.6(e)(3)(viii) Yes
63.6(e)(3)(ix) Yes
63.6(f)(1) No § 63.102(a) of subpart F specifies when the standards apply.
63.6(f)(2)(i) Yes
63.6(f)(2)(ii) Yes—subpart G No—subpart H § 63.152(c)(2) of subpart G specifies the use of monitoring data in determining compliance with subpart G.
63.6(f)(2)(iii) (A), (B), and (C) Yes
63.6(f)(2)(iii)(D) No
63.6(f)(2)(iv) Yes
63.6(f)(2)(v) Yes
63.6(f)(3) Yes
63.6(g) No Procedures specified in § 63.102(b) of subpart F.
63.6(h) No
63.6(i)(1) Yes
63.6(i)(2) Yes
63.6(i)(3) No For subpart G, § 63.151(a)(6) specifies procedures; for subpart H, § 63.182(a)(6) specifies procedures.
63.6(i)(4)(i)(A) Yes
63.6(i)(4)(i)(B) No Dates are specified in § 63.151(a)(6)(i) of subpart G and § 63.182(a)(6)(i) of subpart H.
63.6(i)(4)(ii) No
63.6(i) (5)–(14) Yes
63.6(i)(15) No
63.6(i)(16) Yes
63.6(j) Yes
63.7(a)(1) No Subparts F, G, and H specify required testing and compliance demonstration procedures.
63.7(a)(2) No For subpart G, test results must be submitted in the Notification of Compliance Status due 150 days after compliance date, as specified in § 63.152(b); for subpart H, all test results subject to reporting are reported in periodic reports.
63.7(a)(3) Yes
63.7(b) No
63.7(c) No
63.7(d) Yes
63.7(e)(1) Yes
63.7(e)(2) Yes
63.7(e)(3) No Subparts F, G, and H specify test methods and procedures.
63.7(e)(4) Yes
63.7(f) No Subparts F, G, and H specify applicable methods and provide alternatives.
63.7(g) No Performance test reporting specified in § 63.152(b) of subpart G: Not applicable to subpart H because no performance test required by subpart H.
63.7(h)(1) Yes
63.7(h)(2) Yes
63.7(h)(3) No § 63.103(b)(5) of subpart F specifies provisions for requests to waive performance tests.
63.7(h)(4) No
63.7(h)(5) Yes
63.8(a)(1) Yes
63.8(a)(2) No
63.8(a)(3) No
63.8(a)(4) Yes
63.8(b)(1) Yes
63.8(b)(2) No Subparts G and H specify locations to conduct monitoring.
63.8(b)(3) Yes
63.8(c)(1)(i) Yes
63.8(c)(1)(ii) No For subpart G, submit as part of periodic report required by § 63.152(c); for subpart H, retain as required by § 63.181(g)(2)(ii).
63.8(c)(1)(iii) Yes
63.8(c)(2) Yes
63.8(c)(3) Yes
63.8(c)(4) No Subpart G specifies monitoring frequency by kind of emission point and control technology used (e.g., § 63.111, § 63.120(d)(2), § 63.143, and § 63.152(f)); subpart H does not require use of continuous monitoring systems.
63.8 (c)(5)–(c)(8) No
63.8(d) No
63.8(e) No
63.8 (f)(1)–(f)(3) Yes
63.8(f)(4)(i) No Timeframe for submitting request specified in § 63.151(f) or (g) of subpart G; not applicable to subpart H because subpart H specifies acceptable alternative methods.
63.8(f)(4)(ii) Yes
63.8(f)(4)(iii) No
63.8(f)(5)(i) Yes
63.8(f)(5)(ii) No
63.8(f)(5)(iii) Yes
63.8(f)(6) No Subparts G and H do not require continuous emission monitoring.
63.8(g) No Data reduction procedures specified in § 63.152(f) and (g) of subpart G; not applicable to subpart H.
63.9(a) Yes
63.9(b)(1) No Specified in § 63.151(b)(2) of subpart G; specified in § 63.182(b) of subpart H.
63.9(b)(2) No Initial Notification provisions are specified in § 63.151(b) of subpart G; in § 63.182(b) of subpart H.
63.9(b)(3) No
63.9(b)(4) Yes Except that the notification in § 63.9(b)(4)(i) shall be submitted at the time specified in § 63.151(b)(2)(ii) of subpart G; in § 63.182(b)(2) of subpart H.
63.9(b)(5) Yes Except that the notification in § 63.9(b)(5) shall be submitted at the time specified in § 63.151(b)(2)(ii) of subpart G; in § 63.182 (b)(2) of subpart H.
63.9(c) Yes
63.9(d) Yes
63.9(e) No
63.9(f) No
63.9(g) No
63.9(h) No § 63.152(b) of subpart G and § 63.182 (c) of subpart H specify Notification of Compliance Status requirements.
63.9(i) Yes
63.9(j) Yes Only as related to change to major source status.
63.9(k) Yes Only as specified in § 63.9(j).
63.10(a) Yes
63.10(b)(1) No § 63.103(c) of subpart F specifies record retention requirements.
63.10(b)(2) No § 63.103(c) of subpart F specifies required records.
63.10(b)(3) No
63.10(c) No
63.10(d)(1) No
63.10(d)(2) No § 63.152(b) of subpart G specifies performance test reporting; not applicable to subpart H.
63.10(d)(3) No
63.10(d)(4) Yes
63.10(d)(5) Yes Except that reports required by § 63.10(d)(5) shall be submitted at the time specified in § 63.152(d) of subpart G and in § 63.182(d) of subpart H.
63.10(e) No
63.10(f) Yes
63.11–63.15 Yes

a Wherever subpart A specifies “postmark” dates, submittals may be sent by methods other than the U.S. Mail (e.g., by fax or courier). Submittals shall be sent by the specified dates, but a postmark is not necessarily required.

b The plan, and any records or reports of start-up, shutdown, and malfunction do not apply to Group 2 emission points unless they are included in an emissions average.

[62 FR 2737, Jan. 17, 1997, as amended at 71 FR 20456, Apr. 20, 2006; 85 FR 73887, Nov. 19, 2020]