As required in § 63.11432, you must comply with the requirements of the NESHAP General Provisions (40 CFR part 63, subpart A) as shown in the following table.

Citation Subject Applies to
subpart
QQQQQQ?
Explanation
63.1(a)(1)–(4) General applicability of the General Provisions Yes
63.1(a)(5) Reserved No
63.1(a)(6) General applicability of the General Provisions Yes
63.1(a)(7)–(9) Reserved No
63.1(a)(10)–(12) General applicability of the General Provisions Yes
63.1(b)(1) Initial applicability determination Yes
63.1(b)(2) Reserved No
63.1(b)(3) Record of applicability determination Yes
63.1(c)(1)–(2) Applicability of subpart A of this part after a relevant standard has been set Yes
63.1(c)(3)–(4) Reserved No
63.1(c)(5) Notification requirements for an area source that increases HAP emissions to major source levels Yes
63.1(c)(6) Reclassification Yes
63.1(d) Reserved No
63.1(e) Applicability of permit program before a relevant standard has been set Yes
63.2 Definitions Yes
63.3 Units and abbreviations Yes
63.4 Prohibited activities and circumvention Yes
63.5(a)(1) Applicability of preconstruction review requirements No
63.5(a)(2) Applicability of notification requirements Yes
63.5(b)(1) Requirements for newly constructed and reconstructed sources Yes
63.5(b)(2) Reserved No
63.5(b)(3) Required preconstruction approval required for major source construction and reconstruction No Subpart QQQQQQ does not regulate major sources.
63.5(b)(4) Notification requirements for construction or reconstruction of area sources Yes
63.5(b)(5) Reserved No
63.5(b)(6) Added equipment (or a process change) must be considered part of the affected source and subject to all provisions in the relevant standards Yes
63.5(c) Reserved No
63.5(d) Application for approval of construction or reconstruction No Subpart QQQQQQ does not require an application for construction or reconstruction.
63.5(e) Approval of construction or reconstruction No Subpart QQQQQQ does not require application approval before construction or reconstruction.
63.5(f) Approval of construction or reconstruction based on prior State preconstruction review No Subpart QQQQQQ does not require approval of construction or reconstruction based on prior State preconstruction review.
63.6(a) Compliance with standards and maintenance requirements Yes
63.6(b)(1)–(5) Compliance dates for new and reconstructed sources Yes
63(b)(6) Reserved No
63(b)(7) Compliance dates for new and reconstructed sources Yes
63.6(c)(1)–(2) Compliance dates for existing sources Yes
63.6(c)(3)–(4) Reserved No
63.6(c)(5) Compliance dates for existing sources Yes
63.6(d) Reserved No
63.6(e)(1) Operation and maintenance requirements Yes
63.6(e)(2) Reserved No
63.6(e)(3)(i) Startup, shutdown, and malfunction plan No Subpart QQQQQQ does not require a startup, shutdown, and malfunction plan.
63.6(e)(3)(ii) Reserved No
63.6(e)(3)(iii)–(ix) Startup, shutdown, and malfunction plan No Subpart QQQQQQ does not require a startup, shutdown, and malfunction plan.
63.6(f) Compliance with nonopacity emission standards No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(g) Use of an alternative nonopacity emission standard No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(h)(1) Compliance with opacity and visible emissions standards No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(h)(2)(i) Compliance with opacity and visible emissions standards No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(h)(2)(ii) Reserved No
63.6(h)(2)(iii) Compliance with opacity and visible emissions standards No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(h)(3) Reserved No
63.6(h)(4) Notification of opacity or visible emission observations No Subpart QQQQQQ does not contain emission or opacity limits.
63.6 (h)(5)(i)–(iii) Conduct of opacity or visible emission observations No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(h)(5)(iv) Reserved No
63.6(h)(5)(v) Conduct of opacity or visible emission observations No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(h)(6)–(9) Availability of records and use of continuous opacity monitoring system No Subpart QQQQQQ does not contain emission or opacity limits.
63.6(i) Extension of compliance with emissions standards Yes
63.6(j) Exemption from compliance with emissions standards Yes
63.7 Performance Testing Requirements No Subpart QQQQQQ does not require performance tests.
63.8(a)(1)–(2) Applicability of monitoring requirements No Subpart QQQQQQ does not require monitoring of emissions.
63.8(a)(3) Reserved No
63.8(a)(4) Applicability of monitoring requirements No Subpart QQQQQQ does not require monitoring of emissions.
63.8(b)–(g) Conduct of monitoring No Subpart QQQQQQ does not require monitoring of emissions.
63.9(a) Applicability and general information for notification requirements Yes
63.9(b)(1)–(2) Initial notifications Yes
63.9(b)(3) Reserved No
63.9(b)(4)–(5) Initial notifications Yes
63.9(c)–(d) Extension of compliance and special compliance requirements Yes
63.9(e), (f), (g) Notification of performance test, opacity and visible emission observation, and requirements for sources with continuous monitoring systems No Subpart QQQQQQ does not require monitoring of emissions.
63.9(h)(1)–(3) Notification of compliance status Yes
63.9(h)(4) Reserved No
63.9(h)(5)–(6) Notification of compliance status Yes
63.9(i)–(j) Adjustment to time periods or postmark deadlines for submittal and review of required communications, and change in information already provided Yes
63.9(k) Electronic submission of notifications and reports No Subpart QQQQQQ does not require electronic reporting.
63.10(a)–(b) Recordkeeping and reporting requirement applicability and general information No Subpart QQQQQQ establishes requirements for a report of deviations within 30 days.
63.10(c)(1) Additional recordkeeping requirements for sources with continuous monitoring systems No Subpart QQQQQQ does not require the use of continuous monitoring systems.
63.10(c)(2)–(4) Reserved No
63.10(c)(5)–(8) Additional recordkeeping requirements for sources with continuous monitoring systems No Subpart QQQQQQ does not require the use of continuous monitoring systems.
63.10(c)(9) Reserved No
63.10(c)(10)–(15) Additional recordkeeping requirements for sources with continuous monitoring systems No Subpart QQQQQQ does not require the use of continuous monitoring systems.
63.10(d)–(f) General reporting requirements, additional requirements for sources with continuous monitoring systems, and waiver of recordkeeping or reporting requirements No Subpart QQQQQQ establishes requirements for a report of deviations within 30 days.
63.11 Control device requirements for flares and work practice requirements for monitoring leaks No Subpart QQQQQQ does not require flares and does not require monitoring for leaks.
63.12 State authorities and delegations Yes
63.13 Addresses of state air pollution control agencies and EPA Regional Offices Yes
63.14 Incorporations by Reference Yes
63.15 Availability of information and confidentiality Yes
63.16 Requirements for Performance Track member facilities Yes