40 CFR Appendix Table 9 to Subpart U of Part 63 - Table 9 to Subpart U of Part 63—Routine Reports Required by This Subpart
prev | next
Table 9 to Subpart U of Part 63—Routine Reports Required by This Subpart
Reference | Description of report | Due Date |
---|---|---|
§ 63.506(b) and subpart A | Refer to § 63.506(b), Table 1 of this subpart, and to subpart A | Refer to subpart A. |
§ 63.506(e)(3) | Precompliance Report a | 1. Existing affected sources: December 19, 2000. |
2. New affected sources: with the application for approval of construction or reconstruction. | ||
§ 63.506(e)(4) | Emissions Averaging Plan | September 19, 2000. |
§ 63.506(e)(4)(iv) | Updates to Emissions Averaging Plan | 120 days prior to making the change necessitating the update. |
§ 63.506(e)(5) | Notification of Compliance Status b | Within 150 days after the compliance date. |
§ 63.506(e)(6) | Periodic reports | Semiannually, no later than 60 days after the end of each 6-month period. See § 63.506(e)(6)(i) for the due date for this report. |
§ 63.506(e)(6)(xi) | Quarterly for reports Emissions Averaging | No later than 60 days after the end of each quarter. First report is due with the Notification of Compliance Status. |
§ 63.506(e)(6)(xii) | Quarterly reports upon request of the Administrator | No later than 60 days after the end of each quarter. |
§ 63.506(e)(7)(i) | Storage Vessels Notification of Inspection | At least 30 days prior to the refilling of each storage vessel or the inspection of each storage vessel. |
§ 63.506(e)(7)(ii) | Requests for Approval of a Nominal Control Efficiency for Use in Emissions Averaging | Initial submittal is due with the Emissions Averaging Plan; later submittals are made at the discretion of the owner or operator as specified in § 63.506(e)(7)(ii)(B). |
§ 63.506(e)(7)(iii) | Notification of Change in the Primary Product | For notification under § 63.480(f)(3)(ii)—notification submittal date at the discretion of the owner or operator. c |
For notification under § 63.480(f)(4)(ii)—within 6 months of making the determination. |
a There may be two versions of this report due at different times; one for equipment subject to § 63.502 and one for other emission points subject to this subpart.
b There will be two versions of this report due at different times; one for equipment subject to § 63.502 and one for other emission points subject to this subpart.
c Note that the EPPU remains subject to this subpart until the notification under § 63.480(f)(3)(i) is made.
[66 FR 36928, July 16, 2001]