§ 3212.21 What criteria establish a qualified expansion project for the purpose of obtaining a production incentive?

A qualified expansion project must meet the following criteria:

(a) It must involve substantial capital expenditure. Examples include the drilling of additional wells, retrofitting existing wells and collection systems to increase production rates, retrofitting turbines or power plant components to increase efficiency, adding additional generation capacity to existing plants, and enhanced recovery projects such as augmented injection. Projects that are not associated with substantial capital expenditure, such as opening production valves and operating existing equipment at higher rates, do not qualify as expansion projects.

(b) The project must have the potential to increase the net generation by more than 10 percent over the projected generation without the project, using data from the previous 5 years. If 5 years of data are not available, it is not a qualified expansion project.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 43 - PUBLIC LANDS
Public Laws