44 CFR 204.51 - Application and approval procedures for a fire management assistance grant.

Status message

There are 2 Updates appearing in the Federal Register for 44 CFR 204. View below or at eCFR (GPOAccess)
prev | next
§ 204.51 Application and approval procedures for a fire management assistance grant.
(a) Preparing and submitting an application.
(1) After the approval of a fire management assistance declaration, the State may submit an application package for a grant to the Regional Administrator . The application package must include the SF 424 (Request for Federal Assistance) and FEMA Form 20-16a (Summary of Assurances—Non-construction Programs), as well as supporting documentation for the budget.
(2) The State should submit its grant application within 9 months of the declaration. Upon receipt of the written request from the State, the Regional Administrator may grant an extension for up to 3 months. The State's request must include a justification for the extension.
(b) Fire cost threshold.
(1) We will approve the initial grant award to the State when we determine that the State's application demonstrates either of the following:
(i) Total eligible costs for the declared fire meet or exceed the individual fire cost threshold; or
(ii) Total costs of all declared and non-declared fires for which a State has assumed responsibility in a given calendar year meet the cumulative fire cost threshold.
(2) The individual fire cost threshold for a State is the greater of the following:
(i) $100,000; or
(ii) Five percent × $1.07 × the State population, adjusted annually for inflation using the Consumer Price Index for All Urban Consumers published annually by the Department of Labor.
(3) The cumulative fire cost threshold for a State is the greater of the following:
(i) $500,000; or
(ii) Three times the five percent × $1.07 × the State population as described in § 204.51(b)(2)(ii).
(4) States must document the total eligible costs for a declared fire on Project Worksheets, which they must submit with the grant application.
(5) We will not consider the costs of pre-positioning resources for the purposes of determining whether the grant application meets the fire cost threshold.
(6) When the State's total eligible costs associated with the fire management assistance declaration meet or exceed the fire cost threshold eligible costs will be cost shared in accordance with § 204.61.
(c) Approval of the State's grant application. The Regional Administrator has 45 days from receipt the State's grant application or an amendment to the State's grant application, including attached supporting Project Worksheet(s), to review and approve or deny the grant application or amendment; or to notify the Grantee of a delay in processing funding.
(d) Obligation of the grant. Before we approve the State's grant application, the State must have an up-to-date State Administrative Plan and a Hazard Mitigation Plan that has been reviewed and approved by the Regional Administrator . Once these plans are approved by the Regional Administrator , the State's grant application may be approved and we may begin to obligate the Federal share of funding for subgrants to the Grantee.
(1) State administrative plan.
(i) The State must develop an Administrative Plan (or have a current Administrative Plan on file with FEMA) that describes the procedures for the administration of the Fire Management Assistance Grant Program. The Plan will include, at a minimum, the items listed below:
(A) The designation of the State agency or agencies which will have responsibility for program administration.
(B) The identification of staffing functions for the Fire Management Assistance Program, the sources of staff to fill these functions, and the management and oversight responsibilities of each.
(C) The procedures for:
(1) Notifying potential applicants of the availability of the program;
(2) Assisting FEMA in determining applicant eligibility;
(3) Submitting and reviewing subgrant applications;
(4) Processing payment for subgrants;
(5) Submitting, reviewing, and accepting subgrant performance and financial reports;
(6) Monitoring, close-out, and audit and reconciliation of subgrants;
(7) Recovering funds for disallowed costs;
(8) Processing appeal requests and requests for time extensions; and
(9) Providing technical assistance to applicants and subgrant recipients, including briefings for potential applicants and materials on the application procedures, program eligibility guidance and program deadlines.
(ii) The Grantee may request the Regional Administrator to provide technical assistance in the preparation of the State Administrative Plan.
(2) Hazard Mitigation Plan. As a requirement of receiving funding under a fire management assistance grant, a State, or tribal organization, acting as Grantee, must:
(i) Develop a Mitigation Plan in accordance with 44 CFR part 201 that addresses wildfire risks and mitigation measures; or
(ii) Incorporate wildfire mitigation into the existing Mitigation Plan developed and approved under 44 CFR part 201 that also addresses wildfire risk and contains a wildfire mitigation strategy and related mitigation initiatives.
[66 FR 57347, Nov. 14, 2001, as amended at 68 FR 61371, Oct. 28, 2003]

Title 44 published on 2014-10-01

The following are only the Rules published in the Federal Register after the published date of Title 44.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, DEPARTMENT OF TRANSPORTATION, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF HEALTH AND HUMAN SERVICES, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF LABOR, ENVIRONMENTAL PROTECTION AGENCY, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, DEPARTMENT OF DEFENSE, NATIONAL ENDOWMENT FOR THE HUMANITIES, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 5121 - Congressional findings and declarations

§ 5122 - Definitions

§ 5131 - Federal and State disaster preparedness programs

§ 5132 - Disaster warnings

§ 5133 - Predisaster hazard mitigation

§ 5134 - Interagency task force

§ 5141 - Waiver of administrative conditions

§ 5142 - Repealed.

§ 5143 - Coordinating officers

§ 5144 - Emergency support and response teams

§ 5145, 5146 - Repealed.

§ 5147 - Reimbursement of Federal agencies

§ 5148 - Nonliability of Federal Government

§ 5149 - Performance of services

§ 5150 - Use of local firms and individuals

§ 5151 - Nondiscrimination in disaster assistance

§ 5152 - Use and coordination of relief organizations

§ 5153 - Priority to certain applications for public facility and public housing assistance

§ 5154 - Insurance

§ 5154a - Prohibited flood disaster assistance

§ 5155 - Duplication of benefits

§ 5156 - Standards and reviews

§ 5157 - Penalties

§ 5158 - Availability of materials

§ 5159 - Protection of environment

§ 5160 - Recovery of assistance

§ 5161 - Audits and investigations

§ 5162 - Advance of non-Federal share

§ 5163 - Limitation on use of sliding scales

§ 5164 - Rules and regulations

§ 5165 - Mitigation planning

§ 5165a - Minimum standards for public and private structures

§ 5165b - Management costs

§ 5165c - Public notice, comment, and consultation requirements

§ 5165d - Designation of Small State and Rural Advocate

§ 5170 - Procedure for declaration

§ 5170a - General Federal assistance

§ 5170b - Essential assistance

§ 5170c - Hazard mitigation

§ 5171 - Federal facilities

§ 5172 - Repair, restoration, and replacement of damaged facilities

§ 5173 - Debris removal

§ 5174 - Federal assistance to individuals and households

§ 5175 - Repealed.

§ 5176 - Repealed.

§ 5177 - Unemployment assistance

§ 5177a - Emergency grants to assist low-income migrant and seasonal farmworkers

§ 5178 - Repealed.

§ 5179 - Benefits and distribution

§ 5180 - Food commodities

§ 5181 - Relocation assistance

§ 5182 - Legal services

§ 5183 - Crisis counseling assistance and training

§ 5184 - Community disaster loans

§ 5185 - Emergency communications

§ 5186 - Emergency public transportation

§ 5187 - Fire management assistance

§ 5188 - Timber sale contracts

§ 5189 - Simplified procedure

§ 5189a - Appeals of assistance decisions

§ 5189b - Date of eligibility; expenses incurred before date of disaster

§ 5189c - Transportation assistance to individuals and households

§ 5189d - Case management services

§ 5189e - Essential service providers

§ 5191 - Procedure for declaration

§ 5192 - Federal emergency assistance

§ 5193 - Amount of assistance

§ 5195 - Declaration of policy

§ 5195a - Definitions

§ 5195b - Administration of subchapter

§ 5195c - Critical infrastructures protection

§ 5196 - Detailed functions of administration

§ 5196a - Mutual aid pacts between States and neighboring countries

§ 5196b - Contributions for personnel and administrative expenses

§ 5196c - Grants for construction of emergency operations centers

§ 5196d - Use of funds to prepare for and respond to hazards

§ 5196e - Radiological Emergency Preparedness Fund

§ 5196f - Disaster related information services

§ 5197 - Administrative authority

§ 5197a - Security regulations

§ 5197b - Use of existing facilities

§ 5197c - Annual report to Congress

§ 5197d - Applicability of subchapter

§ 5197e - Authorization of appropriations and transfers of funds

§ 5197f - Relation to Atomic Energy Act of 1954

§ 5197g - Federal Bureau of Investigation

§ 5197h - Minority emergency preparedness demonstration program

§ 5201 - Rules and regulations

§ 5202 - Repealed.

§ 5203 - Excess disaster assistance payments as budgetary emergency requirements

§ 5204 - Insular areas disaster survival and recovery; definitions

§ 5204a - Authorization of appropriations for insular areas

§ 5204b - Technical assistance for insular areas

§ 5204c - Hazard mitigation for insular areas

§ 5205 - Disaster grant closeout procedures

§ 5206 - Buy American

§ 5207 - Firearms policies

Presidential Documents

Executive Order ... 12127

Executive Order ... 12148

Executive Order ... 12673

Reorganization ... 1978 Plan No. 3

Title 44 published on 2014-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 44 CFR 204 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, DEPARTMENT OF TRANSPORTATION, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF HEALTH AND HUMAN SERVICES, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF LABOR, ENVIRONMENTAL PROTECTION AGENCY, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, DEPARTMENT OF DEFENSE, NATIONAL ENDOWMENT FOR THE HUMANITIES, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200