45 CFR 16.15 - Failure to meet deadlines and other requirements.

§ 16.15 Failure to meet deadlines and other requirements.

(a) Since one of the objectives of administrative dispute resolution is to provide a decision as fast as possible consistent with fairness, the Board will not allow parties to delay the process unduly. The Board may grant extensions of time, but only if the party gives a good reason for the delay.

(b) If the appellant fails to meet any filing or procedural deadlines, appeal file or brief submission requirements, or other requirements established by the Board, the Board may dismiss the appeal, may issue an order requiring the party to show cause why the appeal should not be dismissed, or may take other action the Board considers appropriate.

(c) If the respondent fails to meet any such requirements, the Board may issue a decision based on the record submitted to that point or take such other measures as the Board considers appropriate.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


Statutes at Large
Presidential Documents

Reorganization ... 1950 Plan No. 26

Title 45 published on 12-Sep-2017 03:33

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 45 CFR Part 16 after this date.

  • 2016-01-20; vol. 81 # 12 - Wednesday, January 20, 2016
    1. 81 FR 3004 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards; Technical Amendments
      GPO FDSys XML | Text
      DEPARTMENT OF HEALTH AND HUMAN SERVICES
      Interim final rule; technical amendments.
      Effective January 20, 2016. Implementation Date: For all non-Federal entities, there is a two-year grace period for implementation of the procurement standards in 45 CFR 75.326 through 75.335.
      42 CFR Parts 38, 50, 51, 51a, 51b, 51c, 51d, 52, 52a, 52b, 52c, 52d, 52e, 55a, 56, 57, 59, 59a, 62, 63a, 64, 65, 65a, 66, 67, 124, 136, 403, 417, 430, 433, 434, 435, 436, 438, 440, 441, 456, 457, and 1001