47 CFR 1.1422 - Contractors for survey and make-ready.

§ 1.1422 Contractors for survey and make-ready.
(a) A utility shall make available and keep up-to-date a reasonably sufficient list of contractors it authorizes to perform surveys and make-ready in the communications space on its utility poles in cases where the utility has failed to meet deadlines specified in § 1.1420.
(b) If a cable operator or telecommunications carrier hires a contractor for purposes specified in § 1.1420, it shall choose from among a utility's list of authorized contractors.
(c) A cable operator or telecommunications carrier that hires a contractor for survey or make-ready work shall provide a utility with a reasonable opportunity for a utility representative to accompany and consult with the authorized contractor and the cable operator or telecommunications carrier.
(d) The consulting representative of an electric utility may make final determinations, on a nondiscriminatory basis, where there is insufficient capacity and for reasons of safety, reliability, and generally applicable engineering purposes.
[76 FR 26640, May 9, 2011]
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 1.1422 Contractors for survey and make-ready.

(a) A utility shall make available and keep up-to-date a reasonably sufficient list of contractors it authorizes to perform surveys and make-ready in the communications space on its utility poles in cases where the utility has failed to meet deadlines specified in § 1.1420.

(b) If a cable operator or telecommunications carrier hires a contractor for purposes specified in § 1.1420, it shall choose from among a utility's list of authorized contractors.

(c) A cable operator or telecommunications carrier that hires a contractor for survey or make-ready work shall provide a utility with a reasonable opportunity for a utility representative to accompany and consult with the authorized contractor and the cable operator or telecommunications carrier.

(d) The consulting representative of an electric utility may make final determinations, on a nondiscriminatory basis, where there is insufficient capacity and for reasons of safety, reliability, and generally applicable engineering purposes.

[76 FR 26640, May 9, 2011]

Title 47 published on 2015-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR Part 1 after this date.

  • 2015-12-02; vol. 80 # 231 - Wednesday, December 2, 2015
    1. 80 FR 75431 - Expanding the Economic and Innovation Opportunities of Spectrum Through Incentive Auctions
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule; announcement of effective date.
      47 CFR 1.2204(a), (c), (d)(3), and (d)(5) and 73.3700(h)(4) and (6) and FCC Form 177, Application to Participate in a Reverse Incentive Auction, published at 79 FR 48442, August 15, 2014, are effective on December 2, 2015.
      47 CFR Parts 1 and 73