§ 25.133 Period of construction; certification of commencement of operation.

(a)

(1) Each initial license for an earth station governed by this part, except for blanket licenses, will specify as a condition therein the period in which construction of facilities must be completed and station operation commenced. Construction of the earth station must be completed and the station must be brought into operation within 12 months from the date of the license grant except as may be determined by the Commission for any particular application.

(2) Each initial blanket license for multiple earth stations at unspecified locations will specify as a condition therein the period in which station operation must be commenced. The networks in which the mobile earth stations will be operated must be brought into operation within 12 months from the date of the license grant except as may be determined by the Commission for any particular application.

(b)

(1) Each initial license for a transmitting earth station or modified license authorizing operation of an additional transmitting antenna, except for blanket licenses, will also specify as a condition therein that upon completion of construction, the licensee must file with the Commission a certification containing the following information:

(i) The name of the licensee;

(ii) File number of the application;

(iii) Call sign of the antenna;

(iv) Date of the license;

(v) A certification that the facility as authorized has been completed and that each antenna has been tested and found to perform within 2 dB of the applicable pattern specified in § 25.209 or other authorized pattern;

(vi) The date on which the earth station became operational; and

(vii) A statement that the station will remain operational during the license period unless the license is submitted for cancellation.

(2) For earth stations authorized under any blanket licensing provision in this chapter, a certification containing the information in paragraph (b)(1) of this section must be filed when the network is put into operation.

(c) If the facility does not meet the technical parameters set forth in § 25.209, a request for a waiver must be submitted and approved by the Commission before operations may commence.

(d) Each receiving earth station licensed or registered pursuant to § 25.131 must be constructed and placed into service within 6 months after coordination has been completed. Each licensee or registrant must file with the Commission a certification that the facility is completed and operating as provided in paragraph (b) of this section, with the exception of certification of antenna patterns.

[56 FR 24016, May 28, 1991, as amended at 58 FR 68059, Dec. 23, 1993; 59 FR 53327, Oct. 21, 1994; 65 FR 59142, Oct. 4, 2000; 70 FR 32254, June 2, 2005; 78 FR 8421, Feb. 6, 2013; 79 FR 8318, Feb. 12, 2014]

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 47 published on 2015-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR Part 25 after this date.

  • 2015-11-06; vol. 80 # 215 - Friday, November 6, 2015
    1. 80 FR 68815 - Review of Foreign Ownership Policies for Broadcast, Common Carrier and Aeronautical Radio Licensees
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Proposed rule.
      Submit comments on or before December 21, 2015, and replies on or before January 20, 2016. The NPRM contains potential information collection requirements subject to the PRA, Public Law 104-13. OMB, the general public, and other Federal agencies are invited to comment on the potential new and modified information collection requirements contained in this NPRM. If the information collection requirements are adopted, the Commission will submit the appropriate documents to OMB for review under Section 3507(d) of the PRA. OMB, the general public, and other Federal agencies will again be invited to comment on the new and modified information collection requirements adopted by the Commission.
      47 CFR Parts 1, 25, 73, and 74