§ 25.604 Disbursement of grant funds.

(a) The funding official will determine, based on 7 CFR parts 3015, 3016 and 3019, as applicable, whether disbursement of a grant will be by advance or reimbursement.

(b) A “request for advance or reimbursement,” in form and substance satisfactory to USDA, must be completed by the grantee on behalf of itself and all applicable subrecipients and submitted to the funding official.

(c) Requests for advance or reimbursement must identify:

(1) The amount requested for each benchmark activity;

(2) The cumulative amount advanced to date (not inclusive of the current amount requested) for each benchmark activity;

(3) The total USDA EZ/EC grant obligated for each benchmark activity;

(4) The total approved budget for the applicable project or program (inclusive of non USDA EZ/EC grant program sources);

(5) An estimated percentage of completion or progress made in accomplishing the benchmark goal associated with each benchmark activity;

(6) Certification that the lead managing entity and the subrecipients (where applicable) are in compliance with all applicable laws and regulatory requirements; and

(7) Such other information as the funding official may require.

(d) Requests for advance or reimbursement may include only activities or projects which are identified in an approved strategic plan.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 26 - INTERNAL REVENUE CODE
Statutes at Large

Title 7 published on 10-May-2017 03:42

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 7 CFR Part 25 after this date.

  • 2016-03-02; vol. 81 # 41 - Wednesday, March 2, 2016
    1. 81 FR 11000 - Environmental Policies and Procedures
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, Office of the Secretary, Rural Business-Cooperative Service, Rural Utilities Service, Rural Housing Service, Farm Service Agency
      Final rule.
      Effective date: The effective date for the final rule is April 1, 2016. Applicability date: For proposals that had a complete application submitted on or prior to April 1, 2016, either 7 CFR part 1794 or 7 CFR part 1940, subpart G, applies, as applicable. If the application was not complete prior to April 1, 2016, then 7 CFR part 1970 applies.
      7 CFR Part 25