Additional feasible measure

Additional feasible measure is any control measure that otherwise meets the definition of best available control measure (BACM) but can only be implemented in whole or in part beginning 4 years after the date of reclassification of an area as Serious and no later than the statutory attainment date for the area.

Source

40 CFR § 51.1000


Scoping language

The following definitions apply for purposes of this subpart. Any term not defined herein shall have the meaning as defined in 40 CFR 51.100 or Clean Air Act section 302.