claim

The term claim means a written demand by a Contractor, in compliance with this paragraph, for a decision by a Contracting Officer under a disputes clause. A claim must:
(1) State the amount of monetary relief, or the kind of nonmonetary relief, sought, and identify the contract provision relied upon;
(2) Include sufficient supporting data to permit the Contracting Officer to decide the claim, or provide appropriate reference to previously submitted data;
(3) If monetary relief totalling more than $50,000 is involved, include a signed certification by the Contractor that the claim is made in good faith, that the supporting data are accurate and complete to the best of the Contractor's knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the Contractor believes TVA is liable;
(4) Be signed by the Contractor, or on its behalf if the Contractor is other than an individual. If signed on a Contractor's behalf, the claim must include evidence of the authority of the individual so signing it, and of the individual signing any certification required by this paragraph, unless such authority appears in the contract or contract file.

Source

18 CFR § 1308.2


Scoping language

For the purposes of this part, unless otherwise provided:

Is this correct? or