Revisions to wage determinations.

Revisions to wage determinations.
(1) General and project wage determinations may be revised from time to time to keep them current. A revised wage determination replaces the previous wage determination. “Revisions,” as used in this section, refers both to modifications of some or all of the rates in a wage determination, such as periodic updates to reflect current rates, and to instances where a wage determination is re-issued entirely, such as after a new wage survey is conducted. Revisions include adjustments to non-collectively bargained prevailing wage and fringe benefit rates on general wage determinations, with the adjustments based on U.S. Bureau of Labor Statistics Employment Cost Index (ECI) data or its successor data. Such rates may be adjusted based on ECI data no more frequently than once every 3 years, and no sooner than 3 years after the date of the rate's publication. Such periodic revisions to wage determinations are distinguished from the circumstances described in paragraphs (d), (e), and (f) of this section.
(2)
(i) Whether a revised wage determination is effective with respect to a particular contract or project generally depends on the date on which the revised wage determination is issued. The date on which a revised wage determination is “issued,” as used in this section, means the date that a revised general wage determination is published on the DOL-approved website or the date that the contracting agency receives actual written notice of a revised project wage determination.
(ii) If a revised wage determination is issued before contract award (or the start of construction when there is no award), it is effective with respect to the project, except as follows:
(A) For contracts entered into pursuant to sealed bidding procedures, a revised wage determination issued at least 10 calendar days before the opening of bids is effective with respect to the solicitation and contract. If a revised wage determination is issued less than 10 calendar days before the opening of bids, it is effective with respect to the solicitation and contract unless the agency finds that there is not a reasonable time still available before bid opening to notify bidders of the revision and a report of the finding is inserted in the contract file. A copy of such report must be made available to the Administrator upon request. No such report is required if the revision is issued after bid opening.
(B) In the case of projects assisted under the National Housing Act, a revised wage determination is effective with respect to the project if it is issued prior to the beginning of construction or the date the mortgage is initially endorsed, whichever occurs first.
(C) In the case of projects to receive housing assistance payments under section 8 of the U.S. Housing Act of 1937, a revised wage determination is effective with respect to the project if it is issued prior to the beginning of construction or the date the agreement to enter into a housing assistance payments contract is signed, whichever occurs first.
(D) If, in the case of a contract entered into pursuant to sealed bidding procedures under paragraph (c)(2)(ii)(A) of this section the contract has not been awarded within 90 days after bid opening, or if, in the case of projects assisted under the National Housing Act or receiving housing assistance payments section 8 of the U.S. Housing Act of 1937 under paragraph (c)(2)(ii)(B) or (C) of this section, construction has not begun within 90 days after initial endorsement or the signing of the agreement to enter into a housing assistance payments contract, any revised general wage determination issued prior to award of the contract or the beginning of construction, as appropriate, is effective with respect to that contract unless the head of the agency or the agency head's designee requests and obtains an extension of the 90-day period from the Administrator. Such request must be supported by a written finding, which includes a brief statement of the factual support, that the extension is necessary and proper in the public interest to prevent injustice or undue hardship or to avoid serious impairment in the conduct of Government business. The Administrator will either grant or deny the request for an extension after consideration of all the circumstances.
(iii) If a revised wage determination is issued after contract award (or after the beginning of construction where there is no contract award), it is not effective with respect to that project, except under the following circumstances:
(A) Where a contract or order is changed to include additional, substantial construction, alteration, and/or repair work not within the scope of work of the original contract or order, or to require the contractor to perform work for an additional time period not originally obligated, including where an option to extend the term of a contract is exercised, the contracting agency must include the most recent revision of any wage determination(s) at the time the contract is changed or the option is exercised. This does not apply where the contractor is simply given additional time to complete its original commitment or where the additional construction, alteration, and/or repair work in the modification is merely incidental.
(B) Some contracts call for construction, alteration, and/or repair work over a period of time that is not tied to the completion of any particular project. Examples of such contracts include, but are not limited to, indefinite-delivery-indefinite-quantity construction contracts to perform any necessary repairs to a Federal facility over a period of time; long-term operations-and-maintenance contracts that may include construction, alteration, and/or repair work covered by Davis-Bacon labor standards; or schedule contracts or blanket purchase agreements in which a contractor agrees to provide certain construction work at agreed-upon prices to Federal agencies. These types of contracts often involve a general commitment to perform necessary construction as the need arises, but do not necessarily specify the exact construction to be performed. For the types of contracts described here, the contracting agency must incorporate into the contract the most recent revision(s) of any applicable wage determination(s) on each anniversary date of the contract's award (or each anniversary date of the beginning of construction when there is no award) unless the agency has sought and received prior written approval from the Department for an alternative process. The Department may grant such an exception when it is necessary and proper in the public interest or to prevent injustice and undue hardship. Such revised wage determination(s) will apply to any construction work that begins or is obligated under such a contract during the 12 months following that anniversary date until such construction work is completed, even if the completion of that work extends beyond the twelve-month period. Where such contracts have task orders, purchase orders, or other similar contract instruments awarded under the master contract, the master contract must specify that the applicable updated wage determination must be included in such task orders, purchase orders, or other similar contract instrument, and the ordering agency must so incorporate the applicable updated wage determinations into their orders. Once the applicable updated wage determination revision has been incorporated into such task orders, purchase orders, or other similar contract instruments, that wage determination revision remains applicable for the duration of such order, unless the order is changed to include additional, substantial construction, alteration, and/or repair work not within the scope of work, when the wage determination must be updated as set forth in paragraph (c)(2)(iii)(A) of this section, or the order itself includes the exercise of options. Where such orders do include the exercise of options, updated applicable wage determination revision, as incorporated into the master contract must be included when an option is exercised on such an order.
(C) For contracts to which both paragraphs (c)(2)(iii)(A) and (B) of this section apply, updated wage determinations must be incorporated pursuant to the requirements of both paragraphs. For example, if a contract calls for construction, alteration, and/or repair work over a period of time that is not tied to the completion of any particular project and also has an option provision to extend the contract's term, the most recent revision(s) of any applicable wage determination(s) must be incorporated any time an option is exercised, as described in paragraph (c)(2)(iii)(A) of this section, and on the contract anniversary date, as described in paragraph (c)(2)(iii)(B) of this section. However, when a contract has been changed as described in paragraph (c)(2)(iii)(A) of this section, including by the exercise of an option, the date of that modification will be considered the contract anniversary date for the purpose of annually updating the wage determination(s) in accordance with paragraph (c)(2)(iii)(B) of this section for that year and any subsequent years of contract performance.

Source

29 CFR § 1.6