Good faith/all permits standard.

(1) Good faith/all permits standard. All permits and other authorizations required to conduct surface coal mining operations had been obtained, or a good faith effort to obtain all necessary permits and authorizations had been made, before the land came under the protection of 761.11 or 30 U.S.C. 1272(e). At a minimum, an application must have been submitted for any permit required under subchapter G of this chapter or its State program counterpart.

Source

30 CFR § 761.5


Scoping language

For the purposes of this part

Is this correct? or