Reconstruction

Reconstruction will be presumed to have taken place where the fixed capital cost of the new component exceeds 50 percent of the fixed capital cost of a comparable entirely new source. Any final decision as to whether reconstruction has occurred must be made in accordance with the provisions of 60.15 (1) through (3) of this title.

Source

40 CFR § 51.301


Scoping language

For purposes of this subpart: