The term claim means a written demand by a Contractor, in compliance with this paragraph, for a decision by a Contracting Officer under a disputes clause. A claim must:


(3) If monetary relief totalling more than $50,000 is involved, include a signed certification by the Contractor that the claim is made in good faith, that the supporting data are accurate and complete to the best of the Contractor's knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the Contractor believes TVA is liable;

The Contracting Officer has no authority to waive any of the requirements of this paragraph.