Alternate I

Alternate I (JUN 2020). As prescribed in 44.204(2), substitute the following paragraph (e)(2) for paragraph (e)(2) of the basic clause:
(e)
(2) If the Contractor has an approved purchasing system and consent is not required under paragraph (c) or (d) of this clause, the Contractor nevertheless shall notify the Contracting Officer reasonably in advance of entering into any (i) cost-plus-fixed-fee subcontract, or (ii) fixed-price subcontract that exceeds either the simplified acquisition threshold, as defined in FAR 2.101 on the date of subcontract award, or 5 percent of the total estimated cost of this contract. The notification shall include the information required by paragraphs (e)(1)(i) through (iv) of this clause.

Source

48 CFR § 52.244-2