Project wage determinations.

Project wage determinations.
(i) “Project wage determinations” initially issued will be effective for 180 calendar days from the date of such determinations. If a project wage determination is not incorporated into a contract (or, if there is no contract award, if construction has not started) in the period of its effectiveness it is void.
(ii) Accordingly, if it appears that a project wage determination may expire between bid opening and contract award (or between initial endorsement under the National Housing Act or the execution of an agreement to enter into a housing assistance payments contract under section 8 of the U.S. Housing Act of 1937, and the start of construction) the agency must request a new project wage determination sufficiently in advance of the bid opening to assure receipt prior thereto.
(iii) However, when due to unavoidable circumstances a project wage determination expires before award but after bid opening (or before the start of construction, but after initial endorsement under the National Housing Act, or before the start of construction but after the execution of an agreement to enter into a housing assistance payments contract under section 8 of the U.S. Housing Act of 1937), the head of the agency or the agency head's designee may request the Administrator to extend the expiration date of the project wage determination in the bid specifications instead of issuing a new project wage determination. Such request must be supported by a written finding, which must include a brief statement of factual support, that the extension of the expiration date of the project wage determination is necessary and proper in the public interest to prevent injustice or undue hardship or to avoid serious impairment in the conduct of Government business. The Administrator will either grant or deny the request for an extension after consideration of all of the circumstances, including an examination to determine if the previously issued rates remain prevailing. If the request for extension is denied, the Administrator will proceed to issue a new wage determination for the project.

Source

29 CFR § 1.6


Scoping language

None
Is this correct? or