Enforcement.

Enforcement.
(1) Notwithstanding any other provision in this implementation plan, any credible evidence or information relevant to whether the Plant would have been in compliance with applicable requirements if the appropriate performance or compliance test had been performed, can be used to establish whether or not the owner or operator has violated or is in violation of any standard in the plan.
(2) During periods of startup and shutdown the otherwise applicable emission limits or requirements for opacity and particulate matter shall not apply provided that:
(1) Notwithstanding any other provision in this implementation plan, any credible evidence or information relevant to whether the Plant would have been in compliance with applicable requirements if the appropriate performance or compliance test had been performed, can be used to establish whether or not the owner or operator has violated or is in violation of any standard in the plan.
(2) During periods of startup and shutdown the otherwise applicable emission limits or requirements for opacity and particulate matter shall not apply provided that:
(i) At all times the facility is operated in a manner consistent with good practice for minimizing emissions, and the owner or operator uses best efforts regarding planning, design, and operating procedures to meet the otherwise applicable emission limit;
(ii) The frequency and duration of operation in start-up or shutdown mode are minimized to the maximum extent practicable; and
(iii) The owner or operator's actions during start-up and shutdown periods are documented by properly signed, contemporaneous operating logs, or other relevant evidence.
(3) Emissions in excess of the level of the applicable emission limit or requirement that occur due to a malfunction shall constitute a violation of the applicable emission limit. However, it shall be an affirmative defense in an enforcement action seeking penalties if the owner or operator has met with all of the following conditions:
(i) The malfunction was the result of a sudden and unavoidable failure of process or air pollution control equipment or of a process to operate in a normal or usual manner;
(ii) The malfunction did not result from operator error or neglect, or from improper operation or maintenance procedures;
(iii) The excess emissions were not part of a recurring pattern indicative of inadequate design, operation, or maintenance;
(iv) Steps were taken in an expeditious fashion to correct conditions leading to the malfunction, and the amount and duration of the excess emissions caused by the malfunction were minimized to the maximum extent practicable;
(v) All possible steps were taken to minimize the impact of the excess emissions on ambient air quality;
(vi) All emissions monitoring systems were kept in operation if at all possible; and
(vii) The owner or operator's actions in response to the excess emissions were documented by properly signed, contemporaneous operating logs, or other relevant evidence.
(i) Regional Haze Best Available Retrofit Technology limits for this plant are in addition to the requirements of paragraphs (a) through (h) of this section. All definitions and testing and monitoring methods of this section apply to the limits in this paragraph (i) except as indicated in paragraphs (i)(1) through (4) of this section. The interim NOX emission limit in paragraph (i)(2)(ii) of this section shall be effective 180 days after re-start of the unit after installation of add-on post-combustion NOX controls for that unit and until the plant-wide limit goes into effect. The plant-wide NOX limit shall be effective no later than 5 years after October 23, 2012. The owner or operator may elect to meet the plant-wide limit early to remove the individual unit limits. Particulate limits for Units 4 and 5 shall be effective 60 days after restart following the scheduled major outage for Units 4 and 5 in 2013 and 2014.
(1) Particulate Matter from Units 4 and 5 shall be limited to 0.015 lb/MMBtu for each unit as measured by the average of three test runs with each run collecting a minimum of 60 dscf of sample gas and with a duration of at least 120 minutes. Sampling shall be performed according to 40 CFR Part 60 Appendices A-1 through A-3, Methods 1 through 4 and Method 5 or Method 5e. The averaging time for any other demonstration of the particulate matter compliance or exceedance shall be based on a 6-hour average. Particulate testing shall be performed annually as required by paragraph (e)(3) of this section. This test with 120 minute test runs may be substituted and used to demonstrate compliance with the particulate limits in paragraph (d)(2) of this section.
(2) Plant-wide nitrogen oxide emission limits.
(i) The plant-wide nitrogen oxide limit, expressed as nitrogen dioxide (NO2), shall be 0.11 lb/MMBtu as averaged over a rolling 30-calendar day period. NOX emissions for each calendar day shall be determined by summing the hourly emissions measured as pounds of NO2 for all operating units. Heat input for each calendar day shall be determined by adding together all hourly heat inputs, in millions of Btu, for all operating units. Each day the rolling 30-calendar day average shall be determined by adding together that day's and the preceding 29 days' pounds of NO2 and dividing that total pounds of NO2 by the sum of the heat input during the same 30-day period. The results shall be the rolling 30-calendar day-average pound per million Btu emissions of NOX.
(ii) The interim NOX limit for the first 750 MW boiler retrofitted with add-on post-combustion NOX control shall be 0.11 lb/MMBtu, based on a rolling average of 30 successive boiler operating days.
(iii) Schedule for add-on post-combustion NOX controls installation
(A) Within 4 years of the effective date of this rule, FCPP shall have installed add-on post-combustion NOX controls on at least 750 MW (net) of generation to meet the interim emission limit in paragraph (i)(2)(ii)(A) of this section.
(B) Within 5 years of the effective date of this rule, FCPP shall have installed add-on post-combustion NOX controls on all 2060 MW (net) of generation to meet the plant-wide emission limit for NOX in paragraph (i)(2)(i) of this section.
(iv) Testing and monitoring shall use the 40 CFR part 75 monitors and meet the 40 CFR part 75 quality assurance requirements. In addition to these 40 CFR part 75 requirements, relative accuracy test audits shall be performed for both the NOX pounds per hour measurement and the heat input measurement. These shall have relative accuracies of less than 20 percent. This testing shall be evaluated each time the 40 CFR part 75 monitors undergo relative accuracy testing.
(v) If a valid NOX pounds per hour or heat input is not available for any hour for a unit, that heat input and NOX pounds per hour shall not be used in the calculation of the 30 day plant-wide rolling average.
(vi) Upon the effective date of the plant-wide NOX average, the owner or operator shall have installed CEMS and COMS software that complies with the requirements of this section.
(3) In lieu of meeting the NOX requirements of paragraph (i)(2) of this section, FCPP may choose to permanently shut down Units 1, 2, and 3 by January 1, 2014 and meet the requirements of this paragraph to control NOX emissions from Units 4 and 5. By July 31, 2018, Units 4 and 5 shall be retrofitted with add-on post-combustion NOX controls to reduce NOX emissions. Units 4 and 5 shall each meet a 0.098 lb/MMBtu emission limit for NOX expressed as NO2 based on a rolling average of 30 successive boiler operating days. A “boiler operating day” is defined as any 24-hour period between 12:00 midnight and the following midnight during which any fuel is combusted at any time at the steam generating unit. Emissions from each unit shall be measured with the 40 CFR part 75 continuous NOX monitor system and expressed in the units of lb/MMBtu and recorded each hour. A valid hour of NOX data shall be determined per 40 CFR part 75. For each boiler operating day, every valid hour of NOX lb/MMBtu measurement shall be averaged to determine a daily average. Each daily average shall be averaged with the preceding 29 valid daily averages to determine the 30 boiler operating day rolling average. The NOX monitoring system shall meet the data requirements of 40 CFR 60.49Da(e)(2) (at least 90 percent valid hours for all operating hours over any 30 successive boiler operating days). Emission testing using 40 CFR part 60 Appendix A Method 7E may be used to supplement any missing data due to continuous monitor problems. The 40 CFR part 75 requirements for bias adjusting and data substitution do not apply for adjusting the data for this emission limit.
(4) By January 1, 2013, the owner or operator shall submit a letter to the Regional Administrator updating EPA of the status of lease negotiations and regulatory approvals required to comply with paragraph (i)(3) of this section. By December 31, 2013, the owner or operator shall notify the Regional Administrator by letter whether it will comply with paragraph (i)(2) of this section or whether it will comply with paragraph (i)(3) of this section and shall submit a plan and time table for compliance with either paragraph (i)(2) or (3) of this section. The owner or operator shall amend and submit this amended plan to the Regional Administrator as changes occur.
(5) The owner or operator shall follow the requirements of 40 CFR part 71 for submitting an application for permit revision to update its Part 71 operating permit after it achieves compliance with paragraph (i)(2) or (3) of this section.
(j) Dust. Each owner or operator shall operate and maintain the existing dust suppression methods for controlling dust from the coal handling and ash handling and storage facilities. Within ninety (90) days after promulgation of this paragraph, the owner or operator shall develop a dust control plan and submit the plan to the Regional Administrator. The owner or operator shall comply with the plan once the plan is submitted to the Regional Administrator. The owner or operator shall amend the plan as requested or needed. The plan shall include a description of the dust suppression methods for controlling dust from the coal handling and storage facilities, ash handling, storage, and landfills, and road sweeping activities. Within 18 months of promulgation of this paragraph each owner or operator shall not emit dust with opacity greater than 20 percent from any crusher, grinding mill, screening operation, belt conveyor, or truck loading or unloading operation.

Source

40 CFR § 49.5512


Scoping language

None
Is this correct? or