Completion of closure activities.

Completion of closure activities.
(1) Except as provided for in paragraph (f)(2) of this section, the owner or operator must complete closure of the CCR unit:
(i) For existing and new CCR landfills and any lateral expansion of a CCR landfill, within six months of commencing closure activities.
(ii) For existing and new CCR surface impoundments and any lateral expansion of a CCR surface impoundment, within five years of commencing closure activities.
(2)
(i) Extensions of closure timeframes. The timeframes for completing closure of a CCR unit specified under paragraphs (f)(1) of this section may be extended if the owner or operator can demonstrate that it was not feasible to complete closure of the CCR unit within the required timeframes due to factors beyond the facility's control. If the owner or operator is seeking a time extension beyond the time specified in the written closure plan as required by paragraph (b)(1) of this section, the demonstration must include a narrative discussion providing the basis for additional time beyond that specified in the closure plan. The owner or operator must place each completed demonstration, if more than one time extension is sought, in the facility's operating record as required by § 257.105(i)(6) prior to the end of any two-year period. Factors that may support such a demonstration include:
(A) Complications stemming from the climate and weather, such as unusual amounts of precipitation or a significantly shortened construction season;
(B) Time required to dewater a surface impoundment due to the volume of CCR contained in the CCR unit or the characteristics of the CCR in the unit;
(C) The geology and terrain surrounding the CCR unit will affect the amount of material needed to close the CCR unit; or
(D) Time required or delays caused by the need to coordinate with and obtain necessary approvals and permits from a state or other agency.
(ii) Maximum time extensions.
(A) CCR surface impoundments of 40 acres or smaller may extend the time to complete closure by no longer than two years.
(B) CCR surface impoundments larger than 40 acres may extend the timeframe to complete closure of the CCR unit multiple times, in two-year increments. For each two-year extension sought, the owner or operator must substantiate the factual circumstances demonstrating the need for the extension. No more than a total of five two-year extensions may be obtained for any CCR surface impoundment.
(C) CCR landfills may extend the timeframe to complete closure of the CCR unit multiple times, in one-year increments. For each one-year extension sought, the owner or operator must substantiate the factual circumstances demonstrating the need for the extension. No more than a total of two one-year extensions may be obtained for any CCR landfill.
(iii) In order to obtain additional time extension(s) to complete closure of a CCR unit beyond the times provided by paragraph (f)(1) of this section, the owner or operator of the CCR unit must include with the demonstration required by paragraph (f)(2)(i) of this section the following statement signed by the owner or operator or an authorized representative:
(1) Except as provided for in paragraph (f)(2) of this section, the owner or operator must complete closure of the CCR unit:
(i) For existing and new CCR landfills and any lateral expansion of a CCR landfill, within six months of commencing closure activities.
(ii) For existing and new CCR surface impoundments and any lateral expansion of a CCR surface impoundment, within five years of commencing closure activities.
(2)
(i) Extensions of closure timeframes. The timeframes for completing closure of a CCR unit specified under paragraphs (f)(1) of this section may be extended if the owner or operator can demonstrate that it was not feasible to complete closure of the CCR unit within the required timeframes due to factors beyond the facility's control. If the owner or operator is seeking a time extension beyond the time specified in the written closure plan as required by paragraph (b)(1) of this section, the demonstration must include a narrative discussion providing the basis for additional time beyond that specified in the closure plan. The owner or operator must place each completed demonstration, if more than one time extension is sought, in the facility's operating record as required by § 257.105(i)(6) prior to the end of any two-year period. Factors that may support such a demonstration include:
(A) Complications stemming from the climate and weather, such as unusual amounts of precipitation or a significantly shortened construction season;
(B) Time required to dewater a surface impoundment due to the volume of CCR contained in the CCR unit or the characteristics of the CCR in the unit;
(C) The geology and terrain surrounding the CCR unit will affect the amount of material needed to close the CCR unit; or
(D) Time required or delays caused by the need to coordinate with and obtain necessary approvals and permits from a state or other agency.
(ii) Maximum time extensions.
(A) CCR surface impoundments of 40 acres or smaller may extend the time to complete closure by no longer than two years.
(B) CCR surface impoundments larger than 40 acres may extend the timeframe to complete closure of the CCR unit multiple times, in two-year increments. For each two-year extension sought, the owner or operator must substantiate the factual circumstances demonstrating the need for the extension. No more than a total of five two-year extensions may be obtained for any CCR surface impoundment.
(C) CCR landfills may extend the timeframe to complete closure of the CCR unit multiple times, in one-year increments. For each one-year extension sought, the owner or operator must substantiate the factual circumstances demonstrating the need for the extension. No more than a total of two one-year extensions may be obtained for any CCR landfill.
(iii) In order to obtain additional time extension(s) to complete closure of a CCR unit beyond the times provided by paragraph (f)(1) of this section, the owner or operator of the CCR unit must include with the demonstration required by paragraph (f)(2)(i) of this section the following statement signed by the owner or operator or an authorized representative: